Common use of Compensable Delay Formula Clause in Contracts

Compensable Delay Formula. If there is a compensable delay, the Contractor’s total entitlement for the compensable delay damages is the computed result of the following formula: Original Contract Amount divided by the Original Contract Time (in calendar days); the result of which is then multiplied by 0.05 and the result of which is multiplied by the number of calendar days of compensable days allowed under these General Conditions that are beyond the Contract Time. Notwithstanding any other provisions of these General Condition or the Construction Documents, to the extent the Contractor is entitled to receive a markup under Section 18.3, this Section 10.3.2 shall be inapplicable, and the markup provided under Section 18.3 shall be deemed to include all the compensable delay damages provided by this Section 10.3.2.

Appears in 3 contracts

Samples: www.bidnet.com, www.bidnet.com, www.bidnet.com

AutoNDA by SimpleDocs

Compensable Delay Formula. If there is a compensable delay, the Contractor’s total entitlement for the compensable delay damages is the computed result of the following formula: Original Contract Amount divided by the Original Contract Time (in calendar days); the result of which is then multiplied by 0.05 and the result of which is multiplied by the number of calendar days of compensable days allowed under these General Conditions that are beyond the Contract Time. Notwithstanding any other provisions of these General Condition or the Construction Contract Documents, to the extent the Contractor is entitled to receive a markup under Section 18.3, this Section 10.3.2 shall be inapplicable, and the markup provided under Section 18.3 shall be deemed to include all the compensable delay damages provided by this Section 10.3.2.

Appears in 2 contracts

Samples: Price Construction Contract, Price Construction Contract

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.