Commissioning Test. The DG Owner shall notify the Cooperative in writing that installation of the DG Facility is complete and that the interconnection equipment is available for testing at least fifteen (15) working days before DG Owner interconnects the DG Facility with the Cooperative’s distribution system. Cooperative shall thereupon have the right to test the DG Facility and/or be present to witness any testing by the DG Owner of the DG Facility. If the Cooperative waives its right to test the DG Facility by notifying the DG Owner in accordance with this section, the DG Owner may interconnect the DG Facility to the Cooperative’s distribution system upon the earlier to occur of the following: (a) notification from; or (b) fifteen (15) working days after the DG Owner has notified the Cooperative that installation of the DG Facility is complete.