Common use of Application for Payment Clause in Contracts

Application for Payment. On or before the tenth (10th) Day of each month during the performance of the Work, Contractor shall submit to Owner an Application for Payment with respect to that portion of the Work (including Punch List Items) which Contractor has satisfactorily completed during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect to the items of Work set forth in the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to Substantial Completion shall be delivered when required under Section 16.3. Each Application for Payment shall be reasonably detailed and shall be accompanied by supporting Documentation evidencing the achievement of the Milestone pursuant to the Schedule of Values for which the Progress Payment is being requested, shall be accompanied by lien waivers required to be delivered pursuant to Section 8.4 and shall be sent by either (i) written notice, or (ii) electronic mail and confirmed by first class mail (with the date of receipt of the original by first class mail to be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curve. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Substantial Completion shall be due within thirty (30) Days after Owner’s acceptance of the Certificate of Substantial Completion. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days after receipt of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days after resolution of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this Agreement. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Company.

Appears in 1 contract

Samples: Procurement and Construction Agreement

AutoNDA by SimpleDocs

Application for Payment. On or before Contractor shall deliver the Application for Payment to Owner by the tenth (10th) Day of each month during for the performance of the Work, Contractor shall submit to Owner an Application for Payment with respect to that portion of milestones completed and progress in the Work for the prior month (including Punch List Items) which Contractor has satisfactorily completed ), including during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect period prior to the items of Work set forth in NTP Date; provided, that the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to of Block Substantial *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION. 45 Completion and Facility Substantial Completion shall be delivered when required under Section 16.316.3 and Section 16.5, respectively. Each Application for Payment shall be reasonably detailed and shall be accompanied by reasonable supporting Documentation documentation evidencing the achievement of the Milestone milestone pursuant to the Schedule schedule of Values values set forth in Exhibit 9 for which the Progress Milestone Payment is being requested, shall be accompanied by lien waivers required to be delivered otherwise pursuant to Section 8.4 and shall be sent by either (i) written noticefacsimile with confirmation of receipt, and Owner shall be deemed to have received such Application for Payment and the documentation supporting achievement of the relevant milestone on the same date of delivery by Contractor if delivered prior to 5:00 pm Pacific Standard Time; provided, that if such date of delivery is not a Business Day or (ii) electronic mail and confirmed by first class mail (with is delivered after 5:00 pm Pacific Standard Time, then the date of receipt of the original by first class mail to delivery shall be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curveimmediately following Business Day. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt delivery of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Block Substantial Completion and Facility Substantial Completion shall be due within thirty (30) Days after Owner’s 's acceptance of the Certificate of Block Substantial Completion or Certificate of Facility Substantial Completion, as applicable. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute promptly and in any event within fifteen (15) Days after receipt of such Application for Payment and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days after receipt delivery of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days after resolution delivery of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this AgreementApplication for Payment. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Companysubcontracts.

Appears in 1 contract

Samples: Procurement and Construction Agreement (Sunpower Corp)

Application for Payment. On or before the tenth (10th) Day of each month during the performance of the Work, Contractor shall submit to Owner an Application for Payment with respect to that portion of the Work (including Punch List Items) which Contractor has satisfactorily completed during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect to the items of Work set forth in the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to Substantial Completion shall be delivered when required under Section 16.3. Each Application for Payment shall be reasonably detailed and shall be accompanied by supporting Documentation evidencing the achievement of the Milestone pursuant to the Schedule of Values for which the Progress Payment is being requested, shall be accompanied by lien waivers required to be delivered pursuant to Section 8.4 and shall be sent by either (i) written notice, or (ii) electronic mail and confirmed by first class mail (with the date of receipt of the original by first class mail to be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curve. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Substantial Completion shall be due within thirty (30) Days after Owner’s acceptance of the Certificate of Substantial Completion. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days after receipt of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days after resolution of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this Agreement. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Company.

Appears in 1 contract

Samples: Build Transfer Agreement

Application for Payment. On or before Contractor shall deliver the tenth (10th) Day Application for Payment to Owner by the *** of each month during for the performance of the Work, Contractor shall submit to Owner an Application for Payment with respect to that portion of milestones completed and progress in the Work for the prior month (including Punch List Items) which Contractor has satisfactorily completed ), including during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect period prior to the items of Work set forth in NTP Date; provided, that the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to of Block Substantial Completion and Facility Substantial Completion shall be delivered when required under Section 16.316.3 and Section 16.5, respectively. Each Application for Payment shall be reasonably detailed and shall be accompanied by reasonable supporting Documentation documentation evidencing the achievement of the Milestone milestone pursuant to the Schedule schedule of Values values set forth in Exhibit 9 for which the Progress Milestone Payment is being requested, shall be accompanied by lien waivers required to be delivered otherwise pursuant to Section 8.4 and shall be sent by either (i) written noticefacsimile with confirmation of receipt, and Owner shall be deemed to have received such Application for Payment and the documentation supporting achievement of the relevant milestone on the same date of delivery by Contractor if delivered prior to 5:00 pm Pacific Standard Time; provided, that if such date of delivery is not a Business Day or (ii) electronic mail and confirmed by first class mail (with is delivered after 5:00 pm Pacific Standard Time, then the date of receipt of the original by first class mail to delivery shall be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curveimmediately following Business Day. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt delivery of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Block Substantial Completion and Facility Substantial Completion shall be due within thirty (30) Days *** after Owner’s 's acceptance of the Certificate of Block Substantial Completion or Certificate of Facility Substantial Completion, as applicable. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute promptly and in any event within *** after receipt of such Application for Payment and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days *** after receipt delivery of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days *** after resolution delivery of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this AgreementApplication for Payment. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Companysubcontracts.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Sunpower Corp)

Application for Payment. On or before Contractor shall deliver the tenth (10th) Day Application for Payment to Owner by the *** of each month during for the performance of the Work, Contractor shall submit to Owner an Application for Payment with respect to that portion of milestones completed and progress in the Work for the prior month (including Punch List Items) which Contractor has satisfactorily completed ), including during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect period prior to the items of Work set forth in NTP Date; provided, that the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to of Block Substantial Completion and Facility Substantial Completion shall be delivered when required under Section 16.316.3 and Section 16.5, respectively. Each Application for Payment shall be reasonably detailed and shall be accompanied by reasonable supporting Documentation documentation evidencing the achievement of the Milestone milestone pursuant to the Schedule schedule of Values values set forth in Exhibit 9 for which the Progress Milestone Payment is being requested, shall be accompanied by lien waivers required to be delivered otherwise pursuant to Section 8.4 and shall be sent by either (i) written noticefacsimile with confirmation of receipt, and Owner shall be deemed to have received such Application for Payment and the documentation supporting achievement of the relevant milestone on the same date of delivery by Contractor if delivered prior to 5:00 pm Pacific Standard Time; provided, that if such date of delivery is not a Business Day or (ii) electronic mail and confirmed by first class mail (with is delivered after 5:00 pm Pacific Standard Time, then the date of receipt of the original by first class mail to delivery shall be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curveimmediately following Business Day. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt delivery of the Application for Payment; provided that the payments in respect of any Application for Payment delivered prior to the NTP Date shall be made in accordance with Section 8.1(a) and with respect to Block Substantial Completion and Facility Substantial Completion shall be due within thirty (30) Days *** after Owner’s 's acceptance of the Certificate of Block Substantial Completion or Certificate of Facility Substantial Completion, as applicable. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute promptly and in any event within *** after receipt of such Application for Payment and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days *** after receipt delivery of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days *** after resolution delivery of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this AgreementApplication for Payment. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Companysubcontracts.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Sunpower Corp)

Application for Payment. On or before the tenth (10th) Day of each month during the performance of the Work, Contractor shall submit to Owner an Application for Payment (in the form of Exhibit 10) with respect to that portion of the Work (including Punch List Items) which Contractor has satisfactorily completed during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect to the items of Work set forth in the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to Substantial Completion shall be delivered when required under Section 16.3. Each Application for Payment shall be reasonably detailed and shall be accompanied by supporting Documentation evidencing the achievement of the Milestone pursuant to the Schedule of Values for which the Progress Payment is being requested, shall be accompanied by lien waivers required to be delivered pursuant to Section 8.4 4.5 and shall be sent by either (i) written notice, or (ii) electronic mail and confirmed by first class mail (with the date of receipt of the original by first class mail to be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curve. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Substantial Project Mechanical Completion shall be due within thirty (30) Days after Owner’s acceptance of the Certificate of Substantial Completion. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days after receipt of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days after resolution of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this Agreement. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Company.thirty

Appears in 1 contract

Samples: Build Transfer Agreement

AutoNDA by SimpleDocs

Application for Payment. On or before Contractor shall deliver the Application for Payment to Owner by the tenth (10th) Day of each month during for the performance of the Work, Contractor shall submit to Owner an Application for Payment with respect to that portion of milestones completed and progress in the Work for the prior month (including Punch List Items) which Contractor has satisfactorily completed ), including during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect period prior to the items of Work set forth in NTP Date; provided, that the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to of Block Substantial Completion and Facility Substantial Completion shall be delivered when required under Section 16.316.3 and Section 16.5, respectively. Each Application for Payment shall be reasonably detailed and shall be accompanied by reasonable supporting Documentation documentation evidencing the achievement of the Milestone milestone pursuant to the Schedule schedule of Values values set forth in Exhibit 9 for which the Progress Milestone Payment is being requested, shall be accompanied by lien waivers required to be delivered otherwise pursuant to Section 8.4 and shall be sent by either (i) written noticefacsimile with confirmation of receipt, and Owner shall be deemed to have received such Application for Payment and the documentation supporting achievement of the relevant milestone on the same date of delivery by Contractor if delivered prior to 5:00 pm Pacific Standard Time; provided, that if such date of delivery is not a Business Day or (ii) electronic mail and confirmed by first class mail (with is delivered after 5:00 pm Pacific Standard Time, then the date of receipt of the original by first class mail to delivery shall be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curveimmediately following Business Day. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt delivery of the Application for Payment; provided that the payments in respect of any Application for Payment delivered prior to the NTP Date shall be made in accordance with Section 8.1(a) and with respect to Block Substantial Completion and Facility Substantial Completion shall be due within thirty (30) Days days after Owner’s 's acceptance of the Certificate of Block Substantial Completion or Certificate of Facility Substantial Completion, as applicable. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute promptly and in any event within fifteen (15) Days after receipt of such Application for Payment and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days after receipt delivery of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days after resolution delivery of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this AgreementApplication for Payment. Contractor shall be responsible for paying or *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION. 50 ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Companysubcontracts.

Appears in 1 contract

Samples: Procurement and Construction Agreement (Sunpower Corp)

Application for Payment. On or before the tenth (10th) Day of each month during the performance of the Work, Contractor shall submit to Owner an Application for Payment (in the form of Exhibit 10) with respect to that portion of the Work (including Punch List Items) which Contractor has satisfactorily completed during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled to be paid for such month, with respect to the items of Work set forth in the Schedule of Values, the aggregate of the amounts obtained by multiplying (x) the value of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Work, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Application for Payment in respect to Substantial Completion shall be delivered when required under Section 16.3. Each Application for Payment shall be reasonably detailed and shall be accompanied by supporting Documentation evidencing the achievement of the Milestone pursuant to the Schedule of Values for which the Progress Payment is being requested, shall be accompanied by lien waivers required to be delivered pursuant to Section 8.4 4.5 and shall be sent by either (i) written notice, or (ii) electronic mail and confirmed by first class mail (with the date of receipt of the original by first class mail to be the date of receipt). In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curve. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Substantial Project Mechanical Completion shall be due within thirty (30) Days after Owner’s acceptance of the Certificate of Substantial CompletionProject Mechanical Completion Certificate. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute and shall pay to Contractor the undisputed portion in accordance with this Section 8.34.4. If such dispute is resolved within thirty (30) Days after receipt of the Application for Payment, Owner shall make payment of such resolved amounts within thirty (30) Days after resolution of the dispute. No partial payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this Agreement. Contractor shall be responsible for paying or ensuring the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release in the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect of work performed or materials delivered on the Site during the period covered by such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.44.5, Contractor shall deliver to the Title Company, as and when required by the Title Company in order to issue title insurance to any Financing Party and to provide an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed by Contractor and in form and substance acceptable to the Title Company.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement

Application for Payment. On or before Between the tenth first (10th1st) and fifth (5th) Day of each month during the performance of the Workmonth, Contractor shall submit to Owner PSGC an Application for Payment filled out and signed by Contractor invoicing PSGC for (a) Contractor’s good faith estimate of Reimbursable Costs for the following month consistent with respect to that portion of the Work monthly progress report delivered in accordance with Section 5.2.3 (including Punch List Itemsthe “Estimated Reimbursable Costs”), (b) which Contractor has satisfactorily completed during that month and for which Contractor has not been previously paid. Each Application for Payment shall set forth, as the amount of the Contract Price Contractor is entitled Fee Installments to be paid for Milestones completed in the prior month in accordance with the Milestone Values in Appendix J, (c) any amount due for which payment was withheld from an earlier payment and where the cause for such withholding no longer applies, and (d) any other amount due to Contractor pursuant to this Agreement. On or before the seventh (7th) Business Day prior to the last Banking Day of such month, Contractor shall reconcile the current Application for Payment with respect a statement setting forth the actual Reimbursable Costs incurred in the performance of Work in the immediately prior month (the “Actual Reimbursable Costs”) and deliver such reconciled Application for Payment to PSGC in the form attached as Appendix R-2C (“Reconciled Application for Payment”). To the extent the Actual Reimbursable Costs for a prior month exceed the Estimated Reimbursable Costs for that month paid to Contractor, the amount of such excess shall be payable by PSGC pursuant to the items current month’s Reconciled Application for Payment. To the extent the Estimated Reimbursable Costs for a prior month paid to Contractor exceed the Actual Reimbursable Costs for that month, the amount of Work such excess shall be credited to PSGC against the amount requested by Contractor in the current month’s Application for Payment and such credit shall be reflected in the current month’s Reconciled Application for Payment. Until delivery of the Full Notice to Proceed by PSGC, the aggregate amount of Compensation for which Contractor may submit a monthly Application for Payment, or a Reconciled Application for Payment, as the case may be, will not exceed the total limit set forth in the Schedule of ValuesCash Flow Cap Curve contained in Appendix J. The Cash Flow Cap Curve will be adjusted whenever the Target Price is adjusted pursuant to a Change Order or as otherwise (a) provided in this Agreement, or (b) agreed by the aggregate Parties so as to allow timely and efficient completion of the amounts obtained by multiplying (x) Work. Notwithstanding the value foregoing, on the Effective Date of each item of Work set forth in the Schedule of Values and (y) that portion of such item of Workthis Agreement, expressed as a percentage, which has been satisfactorily completed during such month, as verified and approved by Owner, less (z) Retainage (for such month, the “Progress Payment”). The Contractor shall submit an Application for Payment in respect to Substantial Completion shall be delivered when required under Section 16.3. Each Application PSGC for Payment shall be reasonably detailed and shall be accompanied by supporting Documentation evidencing the achievement Estimated Reimbursable Costs for the remaining portion of the Milestone pursuant to then current month and for the Schedule next succeeding month without duplication of Values for which amounts paid under the Progress Payment is being requested, shall be accompanied by lien waivers required to be delivered pursuant to Section 8.4 and shall be sent by either (i) written notice, or (ii) electronic mail and confirmed by first class mail (with the date Letter of receipt of the original by first class mail to be the date of receipt)Intent. In addition, as a condition precedent to Owner’s obligation to make payment, Contractor shall be current in its delivery of Monthly Progress Reports, Weekly Progress Reports and other Documentation required for all periods through the month for which payment is requested. In no event shall the aggregate amounts invoiced by Contractor or payable by Owner under each Application for Payment exceed the aggregate amount of the Contract Price payable cumulatively through such month according to the Cash Flow Curve. Owner shall make all payments of undisputed amounts when they become due, but in any event, no later than thirty (30) Days after receipt of the Application for Payment; provided that the payments in respect of any Application for Payment with respect to Substantial Completion shall be due within thirty (30) Days after Owner’s acceptance of the Certificate of Substantial Completion. If Owner disputes a portion of an Application for Payment, Owner shall notify Contractor of such Dispute and shall pay to Contractor the undisputed portion in accordance with this Section 8.3. If such dispute is resolved within thirty (30) Days after receipt of the Application for Payment, Owner PSGC shall make payment of such resolved amounts amount within thirty ten (3010) Days after resolution of the disputeEffective Date. No partial Thereafter, Applications for Payment and reconciliations between Estimated Reimbursable Costs and Actual Reimbursable Costs as described above shall continue on a monthly basis as otherwise contemplated by this Section 5.2.2; provided, however, payment made under this Agreement shall be construed to be an acceptance or approval by Owner of any part of the Work or to relieve Contractor of any of its obligations under this Agreement. Contractor shall be responsible for paying or ensuring Estimated Reimbursable Costs specified in the payment of all Subcontractors in connection with the Work completed by the Subcontractors in accordance with the terms of their Subcontracts. Lien Releases. Contractor shall submit with each Application for Payment a conditional partial lien release submitted by Contractor in September 2007, will not be due until October 1, 2007. The Parties recognize that, after Final Completion, the form set forth in Exhibit 12A for the amount requested in the current Application for Payment in respect process will be utilized for the invoicing and payment of work performed or materials delivered on the Site Reimbursable Costs incurred during the period covered by Warranty Period; provided, that because such Application for Payment. Both Contractor and its Major Subcontractors shall provide Owner a conditional final lien release in the form set forth in Exhibit 12B as a condition precedent to payment by Owner of the final Application for Payment. In addition to the lien releases described in this Section 8.4amounts cannot be estimated, Contractor shall deliver invoice such amounts in arrears. For example, Reimbursable Costs related to the Title Company, as and when required by the Title Company Warranty claims incurred in order to issue title insurance to any Financing Party and to provide month shall be invoiced in an endorsement thereto with respect to mechanic’s liens pending disbursement coverage, (a) Contractor’s sworn statement and (b) a mechanic’s lien subordination agreement, each executed Application for Payment delivered by Contractor between the first (1st) and in form fifth (5th) Day of the next month. During the Warranty Period, Applications for Payment and substance acceptable to the Title CompanyReconciled Applications for Payment need not be submitted monthly.

Appears in 1 contract

Samples: Procurement and Construction Agreement (Peabody Energy Corp)