Daily Delay Liquidated Damages definition

Daily Delay Liquidated Damages has the meaning set forth in Section 4(c)(ii) of Exhibit F. “Day-Ahead” has the meaning set forth in the CAISO Tariff.
Daily Delay Liquidated Damages has the meaning set forth in Section 3.06(c).
Daily Delay Liquidated Damages has the meaning set forth in Section 4(c)(ii) of Exhibit F.

Examples of Daily Delay Liquidated Damages in a sentence

  • In no event may Seller extend the Commercial Operation Deadline for more than a total of one hundred eighty (180) days by the payment of Daily Delay Liquidated Damages.

  • Seller will be entitled to a refund (without interest) of any estimated Daily Delay Liquidated Damages payments paid by Seller which exceed the amount required to cover the number of days by which the Commercial Operation Deadline was actually extended.

  • The Daily Delay Liquidated Damages payments applicable to days included in any Commercial Operation Deadline extension are nonrefundable and are in addition to, and not a part of, the Development Security.

  • Article Three Seller’s Obligations Southern California Edison QFID# 1212 Chateau Energy Seller shall be entitled to a refund (without interest) of any estimated Daily Delay Liquidated Damages payments paid by Seller which exceed the amount required to cover the number of days by which the Startup Deadline was actually extended.

  • The Daily Delay Liquidated Damages payments applicable to days included in any Startup Deadline extension shall be nonrefundable and are in addition to and not to be considered part of the Development Fee.


More Definitions of Daily Delay Liquidated Damages

Daily Delay Liquidated Damages means $[___] per MW per day.
Daily Delay Liquidated Damages has the meaning set forth in Section 2.8.2.4. “DC” means direct current. [for solar photovoltaic technology]
Daily Delay Liquidated Damages means Liquidated Damages in an amount equal to three hundred dollars ($300) per MW per Day multiplied by the Project Capacity (MW) for each Day: commencing with the Day following the Construction Milestone Date Extended and continuing to and including the Day on which Seller achieves the Construction Milestone; and/or commencing with the Day following the Project COD Target Date Extended and continuing to and including the Day on which the In-Service Date occurs, in case of either clause (i) or (ii) above, up to a maximum of one hundred twenty (120) Days. Day – means twenty-four (24) consecutive hours commencing with the hour ending 0100 EPT through the hour ending 2400 EPT on any calendar day.
Daily Delay Liquidated Damages has the meaning set forth in Section 2.06. “Day-Ahead” has the meaning set forth in the CAISO Tariff.
Daily Delay Liquidated Damages has the meaning in Section 1 of Schedule I.
Daily Delay Liquidated Damages has the meaning set forth in Section Five.6(c).
Daily Delay Liquidated Damages has the meaning set forth in Section 3.06(c). “Defaulting Party” has the meaning set forth in Section 6.01.