WORKS PROGRAMME. (1) The Key Dates are defined in, Schedule – G, Project Construction Schedule (2) The Contractor shall prepare and submit its Works Programme and three month rolling programmes and the detailed requirements contained in Authority’s Requirements, Appendix 1 and 2 of Part A of this Schedule. (3) In compiling its Works Programme and in all subsequent updating and reporting, the Contractor shall make provision for the time required for co-ordinating and completing the design, testing, commissioning and integrated testing of the Works, including, inter alia, design co-ordination periods during which the Contractor shall the review procedures, determining and complying with the requirements of all Government Departments and all others whose consent, permissions, authority or licence is required prior to the execution of any work. (4) The Works Programme shall take full account of the Design Submission Programme.