The 'When Change Request Not Required' clause defines situations where formal change requests are unnecessary for modifications to a project or agreement. Typically, this clause outlines minor changes, routine clarifications, or administrative updates that can be implemented without triggering the formal change control process. By specifying these exceptions, the clause streamlines project management, reduces administrative burden, and ensures that only significant changes require formal documentation and approval.
When Change Request Not Required. Developer may implement and permit a Utility Owner to implement, without a Change Request or Change Order, changes to a Utility Adjustment design that do not vary from the Technical Provisions, but such changes are subject either to TxDOT’s approval as part of a Utility Assembly as provided in Section 6.3.4.5 of the Technical Provisions, or, if the changes are Utility Adjustment Field Modifications, to TxDOT’s review and comment as provided in Section