Updated Work Plan. The Work Plan shall be used as the basis for progress reporting, schedule control and schedule forecasting. As reasonably requested by Cheniere, Willbros shall revise the Work Plan to include the effect of Change Orders and Amendments and to reflect actual Work in progress as agreed with Cheniere, provided, however, Willbros may not modify the Preparation and Material Receipt Commencement Date, the Construction Commencement Date or the Scheduled Mechanical Completion Date without a Change Order being executed in accordance with this Agreement. Each updated Work Plan shall provide the same details and form as required of the Work Plan. Willbros shall prepare schedule and cash flow forecasts on a monthly basis or as requested by Cheniere that reasonably predict the date for Mechanical Completion of the Project. Willbros shall notify Cheniere of any anticipated or actual slippage in the performance of the Work as compared to the Work Plan. Willbros shall provide to Cheniere weekly reports, monthly summaries of such reports, and upon request, all other relevant information concerning any circumstance or condition affecting the Work.
Appears in 2 contracts
Sources: Engineering, Procurement, and Construction Services Agreement (Cheniere Energy Inc), Engineering, Procurement, and Construction Services Agreement (Cheniere Energy Inc)