Common use of TESTING AND COMMISSIONING Clause in Contracts

TESTING AND COMMISSIONING. 33.1 The Design-Builder will prepare and deliver to the Owner, not less than 180 days before the Target Substantial Completion Date, for review under the Review Procedure, a detailed testing and commissioning plan (the “Commissioning Plan”) that is consistent with the requirements for testing and commissioning of the Facility identified in the Statement of Requirements and that sets out the commissioning activities the Design-Builder intends to carry out to commission the Facility. The Commissioning Plan will include, among other things:

Appears in 1 contract

Samples: Design Build Agreement

AutoNDA by SimpleDocs

TESTING AND COMMISSIONING. 33.1 The Design-Builder will prepare and deliver to the Owner, not less than 180 120 days before the Target Building Substantial Completion Date, for review under the Review Procedure, a detailed testing and commissioning plan (the “Commissioning Plan”) that is consistent with the requirements for testing and commissioning of the Facility identified in the Statement of Requirements and that sets setting out the commissioning activities the Design-Builder intends to carry out to commission the Facility. The Commissioning Plan will include, among other thingsincluding:

Appears in 1 contract

Samples: Design Build Agreement

TESTING AND COMMISSIONING. 33.1 35.1 The Design-Builder will prepare and deliver to the Owner, not less than 180 days before the Target Substantial Completion Date, for review under the Review Procedure, a detailed testing and commissioning plan (the “Commissioning Plan”) that is consistent with the requirements for testing and commissioning of the Facility identified in the Statement of Requirements and that sets out the commissioning activities the Design-Builder intends to carry out to commission the Facility. The Commissioning Plan will include, among other things:

Appears in 1 contract

Samples: Design Build Agreement

TESTING AND COMMISSIONING. 33.1 31.1 The Design-Builder will prepare and deliver to the OwnerAuthority, not less than 180 120 days before the Target Substantial Completion Date, for review under the Review Procedure, a detailed testing and commissioning plan (the “Commissioning Plan”) that is consistent with the requirements for testing and commissioning of the Facility identified in the Statement of Requirements and that sets setting out the commissioning activities the Design-Builder intends to carry out to commission the Facility. The Commissioning Plan will include, among other thingsincluding:

Appears in 1 contract

Samples: Design Build Agreement

AutoNDA by SimpleDocs

TESTING AND COMMISSIONING. 33.1 The Design-Builder will prepare and deliver to the Owner, not less than 180 120 days before the Target Substantial Completion Date, for review under the Review Procedure, a detailed testing and commissioning plan (the “Commissioning Plan”) that is consistent with the requirements for testing and commissioning of the Facility identified in the Statement of Requirements and that sets setting out the commissioning activities the Design-Builder intends to carry out to commission the Facility. The Commissioning Plan will include, among other things:including:‌

Appears in 1 contract

Samples: Design Build Agreement

TESTING AND COMMISSIONING. 33.1 31.1 The Design-Builder will prepare and deliver to the Owner, not less than 180 120 days before the Target Substantial Completion Date, for review under the Review Procedure, a detailed testing and commissioning plan (the “Commissioning Plan”) that is consistent with the requirements for testing and commissioning of the Facility identified in the Statement of Requirements and that sets setting out the commissioning activities the Design-Builder intends to carry out to commission the Facility. The Commissioning Plan will include, among other thingsincluding:

Appears in 1 contract

Samples: Design Build Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.