Common use of TEMPORARY SUSPENSION OF THE WORK Clause in Contracts

TEMPORARY SUSPENSION OF THE WORK. The Owner shall have the authority to suspend the work wholly, or in part, for such period or periods as he may deem necessary, due to unsuitable weather, or such other conditions as are considered unfavorable for the prosecution of the work, or for such time as is necessary due to the failure on the part of the Contractor to carry out orders given or perform any or all provisions of the contract. In the event that the Contractor is ordered by the Owner , in writing, to suspend work for some unforeseen cause not otherwise provided for in the contract and over which the Contractor has no control, the Contractor may be reimbursed for actual money expended on the work during the period of shutdown. No allowance will be made for anticipated profits. The period of shutdown shall be computed from the effective date of the Owner 's order to suspend work to the effective date of the Owner 's order to resume the work. Claims for such compensation shall be filed with the Owner within the time period stated in the Owner 's order to resume work. The Contractor shall forward his/her claim information substantiating the amount shown on the claim to the Owner for consideration in accordance with local laws or ordinances. No provision of this article shall be construed as entitling the Contractor to compensation for delays due to inclement weather, for suspensions made at the request of the Contractor, or for any other delay provided for in the contract, plans, or specifications. If it should become necessary to suspend work for an indefinite period, the Contractor shall store all materials in such manner that they will not become an obstruction nor become damaged in any way. The Contractor shall take every precaution to prevent damage or deterioration of the work performed and provide for normal drainage of the work. The Contractor shall erect temporary structures where necessary to provide for traffic on, to, or from the Airport.

Appears in 18 contracts

Samples: Contract Agreement, Contract Agreement, Contract Agreement

AutoNDA by SimpleDocs

TEMPORARY SUSPENSION OF THE WORK. The Owner shall have the authority to suspend the work Work wholly, or in part, for such period or periods as he it may deem necessary, due to unsuitable weather, or such any other conditions as are considered that the Owner deems, in its sole discretion, unfavorable for the prosecution of the workWork, or for such time as is necessary due to the failure on the part of the Contractor to carry out orders given or perform any or all provisions of the contractContract. The Owner’s suspension shall not be grounds for termination by the Contractor. In the event that the Contractor is ordered by the Owner , in writing, to suspend work for some unforeseen cause not otherwise provided for in the contract and over which the Contractor has no controlWork , the Contractor may only be reimbursed for actual money expended on the work Work that it performs by agreement of the Owner during the period of shutdown. No allowance will be made for anticipated profits. The period of shutdown shall be computed from the effective date of the Owner 's order to suspend work Work to the effective date of the Owner 's order to resume the workWork. Claims for such compensation shall be filed with the Owner within the time period stated in the Owner Owner's order to resume workWork. The Contractor shall forward his/her claim information substantiating the amount shown on the claim to the Owner for consideration in accordance with local laws or ordinances. No provision of this article shall be construed as entitling the Contractor to compensation for delays due to inclement weather, for suspensions made at the request of the Contractor, or for any other delay provided for in the contract, plans, or specificationsContract Documents. If it should become necessary to suspend work Work for an indefinite period, the Contractor shall store all materials in such manner that they will not become an obstruction nor become damaged in any way. The Contractor shall take every precaution to prevent damage or deterioration of the work Work performed and provide for normal drainage of the workWork. The Contractor shall erect temporary structures where necessary to provide for traffic on, to, or from the Airport.

Appears in 7 contracts

Samples: Contract Agreement, Contract Agreement, Contract Agreement

TEMPORARY SUSPENSION OF THE WORK. The Owner Airport Authority shall have the authority to suspend the work Work wholly, or in part, for such period or periods as he may deem necessary, due to unsuitable weather, or such other conditions as are considered unfavorable for the prosecution of the workWork, or for such time as is necessary due to the failure on the part of the Contractor CMR to carry out orders given or perform any or all provisions of the contractContract. In the event that the Contractor CMR is ordered by the Owner Airport Authority, in writing, to suspend work Work for some unforeseen cause not otherwise provided for in the contract Contract and over which the Contractor CMR has no control, the Contractor CMR may be reimbursed for actual money expended on the work Work during the period of shutdown. No allowance will be made for anticipated profits. The period of shutdown shall be computed from the effective date of the Owner 's Design Professional’s order to suspend work Work to the effective date of the Owner 's Design Professional’s order to resume the workWork. Claims for such compensation shall be filed with the Owner Design Professional within the time period stated in the Owner 's Design Professional’s order to resume workWork. The Contractor CMR shall forward submit with his/her claim information substantiating the amount shown on the claim. The Design Professional will forward the CMR’s claim to the Owner Airport Authority for consideration in accordance with local laws or ordinances. No provision of this article shall be construed as entitling the Contractor CMR to compensation for delays due to inclement weather, for suspensions made at the request of the ContractorAirport Authority, or for any other delay provided for in the contractContract, plansPlans, or specificationsSpecifications. If it should become necessary to suspend work Work for an indefinite period, the Contractor CMR shall store all materials Materials in such manner that they will not become an obstruction nor become damaged in any way. The Contractor He shall take every precaution to prevent damage or deterioration of the work Work performed and provide for normal drainage of the workWork. The Contractor CMR shall erect temporary structures where necessary to provide for traffic on, to, or from the Airport.

Appears in 1 contract

Samples: www.flylansing.com

AutoNDA by SimpleDocs

TEMPORARY SUSPENSION OF THE WORK. The Owner shall have the authority to suspend the work wholly, or in part, for such period or periods as he may deem necessary, due to unsuitable weather, or such other conditions as are considered unfavorable for the prosecution of the work, or for such time as is necessary due to the failure on the part of the Contractor to carry out orders given or perform any or all provisions of the contract. In the event that the Contractor is ordered by the Owner Owner, in writing, to suspend work for some unforeseen cause not otherwise provided for in the contract and over which the Contractor has no control, the Contractor may be reimbursed for actual money expended on the work during the period of shutdown. No allowance will be made for anticipated profits. The period of shutdown shall be computed from the effective date of the Owner 's order to suspend work to the effective date of the Owner 's order to resume the work. Claims for such compensation shall be filed with the Owner within the time period stated in the Owner 's order to resume work. The Contractor shall forward his/her claim information substantiating the amount shown on the claim to the Owner for consideration in accordance with local laws or ordinances. No provision of this article shall be construed as entitling the Contractor to compensation for delays due to inclement weather, for suspensions made at the request of the Contractor, or for any other delay provided for in the contract, plans, or specifications. If it should become necessary to suspend work for an indefinite period, the Contractor shall store all materials in such manner that they will not become an obstruction nor become damaged in any way. The Contractor shall take every precaution to prevent damage or deterioration of the work performed and provide for normal drainage of the work. The Contractor shall erect temporary structures where necessary to provide for traffic on, to, or from the Airport.

Appears in 1 contract

Samples: Contract Agreement