Starting and Completion Dates. Construction under this contract shall begin upon notice to proceed by the Owner and be completed in the following stages shown as additions to the notice to proceed date in calendar days: Starting Date 10 days after notice to proceed Isolation 60 calendar days after notice to proceed
Appears in 1 contract
Sources: Construction Contract (Alliance Farms Cooperative Association)
Starting and Completion Dates. Construction under this contract shall begin upon notice to proceed by the Owner and be completed in the following stages shown as additions to the notice to proceed date in calendar days: Starting Date 10 days after notice to proceed Isolation 60 Office Area 140 calendar days after notice to proceed Breeding 150 calendar days after notice to proceed Gestation 180 calendar days after notice to proceed Farrowing 220 calendar days after notice to proceed
Appears in 1 contract
Sources: Construction Contract (Alliance Farms Cooperative Association)