Single Audit Report. A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200. B. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ . C. If expenditures are less than the threshold during Local Government's fiscal year, Local Government must submit a statement to TxDOT's Compliance Division as follows: We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY . D. For each year Project remains open for federal funding expenditures, Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 11 contracts
Sources: Advance Funding Agreement, Advance Funding Agreement, Advance Funding Agreement
Single Audit Report. A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 98-502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200.
B. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ ▇.
C. If expenditures are less than the threshold during the Local Government's fiscal year, the Local Government must submit a statement to TxDOT's Compliance Division as follows: "We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY ."
D. For each year Project the project remains open for federal funding expenditures, the Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project the project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 8 contracts
Sources: Advance Funding Agreement, Advance Funding Agreement, Local Project Advance Funding Agreement
Single Audit Report. A. 20.1. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 50298‐502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200.
B. 20.2. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ .
C. ▇. If expenditures are less than the threshold during Local Government's fiscal year, Local Government must submit a statement to TxDOT's Compliance Division as follows: We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY .
D. 20.3. For each year Project remains open for federal funding expenditures, Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 2 contracts
Sources: Local Project Advance Funding Agreement, Local Project Advance Funding Agreement
Single Audit Report. A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200.
B. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ ▇.
C. If expenditures are less than the threshold during the Local Government's fiscal year, the Local Government must submit a statement to TxDOT's Compliance Division as follows: "We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY ."
D. For each year Project the project remains open for federal funding expenditures, the Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project the project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 1 contract
Sources: Local Project Advance Funding Agreement for Non Construction
Single Audit Report. A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 98-502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200OMB Circular A-133.
B. If threshold expenditures of $750,000 or more are met during the Local Government's fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance DivisionAudit Office, ▇▇▇ ▇▇▇▇ . ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division Audit Office at ▇▇▇▇://▇▇▇▇▇▇▇▇@.▇▇▇▇▇.▇▇▇ ▇/inside-txdot/office/audit/contact.html.
C. If expenditures are less than $750,000 during the threshold during Local Government's fiscal year, the Local Government must submit a statement to TxDOT's Compliance Division Audit Office as follows: "We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY .the
D. For each year Project the project remains open for federal funding expenditures, the Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project the project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 1 contract
Single Audit Report. If federal funds are used:
A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 502, ensuring that the single audit report includes the coverage requirements stipulated in 2 CFR Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards.
B. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division by email at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ ▇.
C. If expenditures are less than the threshold during the Local Government's fiscal year, the Local Government must submit a statement to TxDOT's Compliance Division as follows: "We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY ."
D. For each year the Project remains open for federal funding expenditures, the Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreementAgreement, unless otherwise amended or the Project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 1 contract
Sources: Advance Funding Agreement
Single Audit Report. A. If federal funds are used: The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 502, ensuring that the single audit report includes the coverage requirements stipulated in 2 CFR Part 200.
B. , Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division by email at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ .
C. ▇. If expenditures are less than the threshold during the Local Government's fiscal year, the Local Government must submit a statement to TxDOT's Compliance Division as follows: "We did not meet the $ $______ expenditure threshold and therefore, are not required to have a single audit performed for FY ______.
D. " For each year the Project remains open for federal funding expenditures, the Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreementAgreement, unless otherwise amended or the Project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 1 contract
Sources: Advance Funding Agreement
Single Audit Report. A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200OMB Circular A-133.
B. If threshold expenditures of $750,000 500,000 or more are met during the Local Government's fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance DivisionAudit Office, ▇▇▇ ▇▇▇▇ . ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ .Audit Office at
C. If expenditures are less than $500,000 during the threshold during Local Government's fiscal year, the Local Government must submit a statement to TxDOT's Compliance Division Audit Office as follows: "We did not meet the $ $500,000 expenditure threshold and therefore, are not required to have a single audit performed for FY ."
D. For each year Project the project remains open for federal funding expenditures, the Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project the project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 1 contract
Sources: Advance Funding Agreement
Single Audit Report. A. The parties shall comply with the requirements of the Single Audit Act of 1984, P.L. 98- 502, ensuring that the single audit report includes the coverage stipulated in 2 CFR Part 200.
B. If threshold expenditures of $750,000 or more are met during the fiscal year, the Local Government must submit a Single Audit Report and Management Letter (if applicable) to TxDOT's Compliance Division, ▇▇▇ ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇, ▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ or contact TxDOT’s Compliance Division at ▇▇▇▇▇▇▇▇▇▇▇▇@▇▇▇▇▇.▇▇▇ .
C. If expenditures are less than the threshold during Local Government's fiscal year, Local Government must submit a statement to TxDOT's Compliance Division as follows: We did not meet the $ expenditure threshold and therefore, are not required to have a single audit performed for FY .. DRAFT
D. For each year Project remains open for federal funding expenditures, Local Government will be responsible for filing a report or statement as described above. The required annual filing shall extend throughout the life of the agreement, unless otherwise amended or Project has been formally closed out and no charges have been incurred within the current fiscal year.
Appears in 1 contract
Sources: Advance Funding Agreement