Schematic Design Documents Review. 5.4.6.1 After the Contracting Authority and Owner have had a reasonable period to review the provisional Schematic Design Documents and the CM’s Schematic Design Stage Submission, the Contracting Authority, Owner, A/E, and CM shall meet to discuss the submissions and reach agreement on any Owner-authorized adjustments to the Approved Program of Requirements, Project Schedule, or Construction Budget and any necessary clarifications of the provisional Schematic Design Documents and the CM’s Schematic Design Stage Submission. .1 Unless the Contracting Authority agrees otherwise in writing, within five business days after the review meeting, the A/E and CM shall revise their respective submissions to reflect the adjustments and clarifications agreed upon in the review meeting, and resubmit those documents to each other, the Owner, and Contracting Authority. 5.4.6.2 When the Contracting Authority and Owner approve the revised Schematic Design submissions and sign the related Design Review Acceptance form, the revised Schematic Design submissions shall become the final Schematic Design Documents.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Professional Services
Schematic Design Documents Review. 5.4.6.1 3.7.1 After the Contracting Authority and Owner have had a reasonable period to review the provisional Schematic Design Documents and the CM’s Schematic Design Stage SubmissionDocuments, the Contracting Authority, Owner, A/E, and CM shall meet to discuss the submissions provisional Schematic Design Documents and CM’s Schematic Design Stage Submission and to reach agreement on any Owner-Contracting Authority- authorized adjustments to the Approved Program of Requirements, Project Schedule, Construction Budget, or Construction Project Budget and any necessary clarifications of the provisional Schematic Design Documents and the CM’s Schematic Design Stage Submission.
.1 3.7.2 Unless the Contracting Authority agrees otherwise in writing, within five 5 business days after the review meeting, the A/E and CM shall revise their respective Schematic Design submissions to reflect the adjustments and clarifications agreed upon in the review meeting, and resubmit those documents to each other, the Owner, and Contracting Authority.
5.4.6.2 3.7.3 When the Contracting Authority and the Owner approve the revised Schematic Design submissions and sign the related Design Review Acceptance form, the revised Schematic Design submissions shall become the final Schematic Design Documents.
Appears in 1 contract
Sources: Professional Services