Common use of Schedule and Completion Clause in Contracts

Schedule and Completion. The Work to be performed under the Contract Documents shall be commenced upon execution of this Contract and shall be completed in accordance with the approved Overall Project Schedule not later than 30 days after the Material Completion and Occupancy Date set forth above. The Guaranteed Maximum Price (GMP). A GMP will be established in accordance with Section 3, Part 3 of the General Requirements. The GMP may be replaced by a Lump Sum Price as set forth in Article 3.3.7 of the General Requirements.

Appears in 4 contracts

Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

AutoNDA by SimpleDocs

Schedule and Completion. The Design and Work to be performed under the Contract Documents shall be commenced upon execution of this Contract and shall be completed in accordance with the approved Overall Project Schedule not later than 30 days after the Material Completion and Occupancy Date set forth above. The Guaranteed Maximum Price (GMP). A GMP will be established in accordance with Section 3, Part 3 of the General Requirements. The GMP may be replaced by a Lump Sum Price as set forth in Article 3.3.7 of the General Requirements.

Appears in 1 contract

Samples: Design Build Contract

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.