Common use of Requirements for Change Order payments Clause in Contracts

Requirements for Change Order payments. 14.4.4.1 The Department and the Contractor are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 10 contracts

Samples: Agreement, Agreement, Agreement

AutoNDA by SimpleDocs

Requirements for Change Order payments. 14.4.4.1 Section 8.28.4.1 The Department and the Contractor A/E are prohibited from requiring a prime contractor (the A/E in this Agreement) or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting OfficerCO:

Appears in 10 contracts

Samples: Agreement, Agreement, Agreement

Requirements for Change Order payments. 14.4.4.1 Section 8.28.4.1 The Department and the Contractor A/E are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 6 contracts

Samples: Agreement, Agreement, Agreement

Requirements for Change Order payments. 14.4.4.1 15.4.4.1 The Department and the Contractor Design-Builder are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a DistrictDepartment-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 4 contracts

Samples: Design Build Agreement, Agreement, Agreement

Requirements for Change Order payments. 14.4.4.1 14.5.4.1 The Department and the Contractor are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 4 contracts

Samples: Agreement, Risk Agreement, Agreement

Requirements for Change Order payments. 14.4.4.1 Section 15.5.4.1 The Department and the Contractor are prohibited from requiring a prime contractor or a subcontractor Subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractorSubcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-to- exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 3 contracts

Samples: Agreement, Agreement, Agreement

AutoNDA by SimpleDocs

Requirements for Change Order payments. 14.4.4.1 15.5.4.1 The Department and the Contractor are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 2 contracts

Samples: Agreement, Agreement

Requirements for Change Order payments. 14.4.4.1 Section 15.5.4.1 The Department and the Contractor are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractor's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-to- exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 2 contracts

Samples: Design Build Agreement, Agreement

Requirements for Change Order payments. 14.4.4.1 15.5.4.1 The Department and the Contractor Design-Builder are prohibited from requiring a prime contractor or a subcontractor to undertake any work that is determined to be beyond the original scope of the prime contractorDesign-Builder's or a subcontractor's contract or subcontract, including work under a District-issued change order, when the additional work increases the contract price beyond the not-to-exceed price or negotiated maximum price of the underlying contract, unless the Contracting Officer:

Appears in 1 contract

Samples: Agreement