Common use of REQUESTS FOR INFORMATION OR APPROVAL Clause in Contracts

REQUESTS FOR INFORMATION OR APPROVAL. 43.1. From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required), the Contractor shall submit to the Project Manager a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager a sufficient time to act upon such submissions, or any necessary re- submissions thereof.

Appears in 10 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

REQUESTS FOR INFORMATION OR APPROVAL. 43.110.1. From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required)schedule, the Contractor shall submit to the Project Manager Engineer a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager Engineer a sufficient time to act upon such submissions, or any necessary re- re-submissions thereof.

Appears in 10 contracts

Samples: Supply and Service Agreement, Supply and Service Agreement, a856-cityrecord.nyc.gov

REQUESTS FOR INFORMATION OR APPROVAL. 43.1. 10.1 From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required)schedule, the Contractor shall submit to the Project Manager Engineer a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager Engineer a sufficient time to act upon such submissions, or any necessary re- re-submissions thereof.

Appears in 10 contracts

Samples: Construction Contract, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

REQUESTS FOR INFORMATION OR APPROVAL. 43.1. From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required), the Contractor shall submit to the Engineer or Project Manager a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Engineer or Project Manager a sufficient time to act upon such submissions, or any necessary re- re-submissions thereof.

Appears in 6 contracts

Samples: Furnish and Install Agreement, Furnish and Install Agreement, a856-cityrecord.nyc.gov

REQUESTS FOR INFORMATION OR APPROVAL. 43.1. 10.1 From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required)schedule, the Contractor shall submit to the Project Manager Engineer a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager Engineer a sufficient time to act upon such submissions, or any necessary re- submissions thereof.

Appears in 2 contracts

Samples: Agreement, Agreement

AutoNDA by SimpleDocs

REQUESTS FOR INFORMATION OR APPROVAL. 43.144.1. From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required), the Contractor shall submit to the Project Manager a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager a sufficient time to act upon such submissions, or any necessary re- submissions thereof.

Appears in 2 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

REQUESTS FOR INFORMATION OR APPROVAL. 43.1. 10.1 From time to time as the Work progresses and in the sequence indicated by the approved progress schedule (if required)schedule, the Contractor shall submit to the Project Manager Director a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager Director a sufficient time to act upon such submissions, or any necessary re- submissions thereof.

Appears in 1 contract

Samples: Agreement, Made And

REQUESTS FOR INFORMATION OR APPROVAL. 43.1. 10.1 From time to time as the Work progresses and in the sequence indicated by the approved accepted progress schedule (if required)schedule, the Contractor shall submit to the Project Manager Engineer a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Project Manager Engineer a sufficient time to act upon such submissions, or any necessary re- re-submissions thereof.

Appears in 1 contract

Samples: www.bidnet.com