Project Scheduling. Prepare an overall project design schedule detailing the progression of the work. This schedule will include review dates by the Program Manager KCI, submittal dates for deliverables, andestimated time frame to complete the work. The schedule will be updated monthly and included in the progress report. Changes or adjustments in the schedule caused by delays due to unforeseen task difficulties or lengthy review times will be shown and reported to the Program Manager KCI. 140 - Progress Meetings • Attend coordination and interim progress review meetings every month or as necessary, to be scheduled on an as-needed basis. Prepare and distribute meeting minutes within five working days after the meeting.