Progress Control Clause Samples
The Progress Control clause establishes mechanisms for monitoring and managing the advancement of work under a contract. It typically requires the contractor to provide regular updates, schedules, or reports detailing the status of the project, and may allow the client to inspect progress or request corrective actions if delays or issues are identified. This clause ensures that the project stays on track, enables early detection of potential problems, and helps both parties maintain transparency and accountability throughout the contract period.
Progress Control. The parties acknowledge and agree that time is of the essence. The DEPARTMENT will provide the CONSULTANT with project and deliverable deadlines for each work order. Unless otherwise indicated in writing by the DEPARTMENT, the CONSULTANT will complete the work in accordance with these deadlines.
Progress Control. 15.3.1 Contractor shall ensure that the monitoring and control of the performance of the Work are carried out in a manner consistent with the planning, progress control and reporting requirements of the Agreement as specified in Schedule E (Contract Coordination Procedures) and Schedule A (Scope of Work).
15.3.2 Contractor shall submit for Approval with the Contract Schedule, (i) a detailed list of the critical path items associated with the Contract Schedule and (ii) the corresponding Work progress control procedures to be utilized for the regular evaluation of the physical progress of the Work as well as the critical path items.
15.3.3 Canadian Natural shall not Approve any Work progress figures unless resulting from the proper implementation of the appropriate Approved progress control procedures. The Approved Work progress figures shall be used as the basis for the preparation of the invoices provided for in Schedule B (Compensation).
Progress Control. Progress Control is another responsibility of the Project Manager and is the monitoring of the project and the production of regular progress reports to communicate the progress of the project to all stakeholders of the project. As most projects do not go exactly to plan, the process of progress control is to keep an eye on the direction of the project and monitor the degree to which the plan is followed and take appropriate action if stages are deviating from the plan by employing regular project tracking. This is achieved by having regular checkpoints during the course of the project that will have been established in the project definition. These meetings may be weekly and are used to monitor and control all that is going on with the project as well as capture statistics from each project team member on actual start and finish dates for their allocated tasks as well as estimates for the next round of tasks.