Programming constraints. A comprehensive and fully detailed programme is to be submitted within the seven (7) days after the inaugural meeting and should be in MS Project format, indicating all milestones and critical dates. This programme must first be approved by the Project Manager and must be updated monthly or as requested by the Project Manager. Only MS Projects format will be allowed. The following dates shall be clearly reflected on the programme: Starting and completion dates for all activities as well as relevant key dates for hold or witness points. All relevant significant activities shall be shown in order to monitor the progress on site or in the workshop. The programme shall also reflect a 2-week period for inspection and correcting of Defects before the completion date. Updated programmes must be available at all site meetings reflecting progress to date.