Programming constraints. a) The Contractor submits a first programme to the Project Manager for acceptance within the period stated in the Contract Data. b) This programme complies with CLAUSE 31.
Appears in 2 contracts
Sources: Nec3 Engineering & Construction Contract, Nec3 Engineering & Construction Contract
Programming constraints. a) The Contractor submits a first programme to the Project Manager for acceptance within the period stated in the Contract Data.
b) This programme complies with CLAUSE 3131.2 • The Accepted Program:
a) Is represented by a recognised planning system which both complies with NWP 5227. Documentation for Project Programming and Contract Progress Monitoring and is submitted to the Project Manager for his acceptance.
b) Indicates the activities of the Contractor, its sub-Contractors, and the interfaces between itself, its sub-Contractors and others as listed in Section 6.10.1.1
Appears in 1 contract