Program Documents Review. 5.3.5.1 After the Contracting Authority and Owner have had a reasonable period to review the provisional Program Documents and the CM’s Program Verification Stage Submission, the Contracting Authority, Owner, A/E, and CM shall meet to discuss the submissions and reach agreement on any Contracting Authority-authorized adjustments to the Project Schedule, Construction Budget, or Project Budget and any necessary clarifications of the provisional Program Documents and the CM’s Program Verification Stage Submission. 5.3.5.2 Unless the Contracting Authority agrees otherwise in writing, within five business days after the review meeting, the A/E and CM shall revise their respective Program Verification submissions to reflect the adjustments and clarifications agreed upon in the review meeting, and resubmit those documents to each other, the Owner, and Contracting Authority. 5.3.5.3 When the Contracting Authority and the Owner approve the revised Program Verification submissions and sign the related Design Review Acceptance form, the revised Program Verification submissions shall become the Approved Program of Requirements.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Professional Services
Program Documents Review. 5.3.5.1 2.7.1 After the Contracting Authority and Owner have had a reasonable period to review the provisional Program Documents and the CM’s Program Verification Stage Submission, the Contracting Authority, Owner, A/E, and CM shall meet to discuss the submissions provisional Program Documents and the Contractor’s Program Verification Stage Submission and reach agreement on any Contracting Authority-authorized adjustments to the Project Schedule, Construction Budget, or Project Budget and any necessary clarifications of the provisional Program Documents and the CM’s Program Verification Stage Submission.
5.3.5.2 2.7.2 Unless the Contracting Authority agrees otherwise in writing, within five 5 business days after the review meeting, the A/E and CM shall revise their respective Program Verification submissions to reflect the adjustments and clarifications agreed upon in the review meeting, and resubmit those documents to each other, the Owner, and Contracting Authority.
5.3.5.3 2.7.3 When the Contracting Authority and the Owner approve the revised Program Verification submissions and sign the related Design Review Acceptance form, the revised Program Verification submissions shall become the Approved Program of Requirements.
Appears in 1 contract
Sources: Professional Services