Pre-Construction Services. Contractor shall provide pre-construction services to Owner as follows: 5.1.1 Contractor shall work with the Architect and Owner to review schematic design, design development and construction drawings for the Project, to evaluate proposed systems and materials, to make recommendations regarding systems and materials which may improve cost effectiveness of the Project or accelerate the schedule. 5.1.2 Contractor shall provide a proposed Project Schedule based upon the schematic design. Project Schedule should show substantial completion dates for the Project no later than set forth on Exhibit 5. Project schedule should include all activities and milestones to take the Project from schematic design to occupancy. Scheduled activities will include meetings, design and construction document time frames, procurement delivery dates, permitting, approvals of authorities, coordination time frames and construction dates. 5.1.3 Contractor shall provide budget development and cost evaluation consisting of estimating, value analysis and life cycle analysis. Estimates shall be prepared at schematic design and design development. Interim estimate revisions shall be prepared any time there is a significant design change. Proposed systems shall be evaluated for first cost, constructability, annual maintenance costs, annual utility costs, life expectancy and schedule impact.
Appears in 3 contracts
Sources: Construction Management Contract, Construction Management Contract, Construction Management Contract
Pre-Construction Services. Contractor shall provide pre-construction services to Owner as follows:
5.1.1 Contractor shall work with the Architect and Owner to review schematic design, design development and construction drawings for the Project, to evaluate proposed systems and materials, to make recommendations regarding systems and materials which may improve cost effectiveness of the Project or accelerate the schedule.
5.1.2 Contractor shall provide a proposed Project Schedule based upon the schematic design. Project Schedule should show substantial completion dates for the Project no later than set forth on Exhibit 5. Project schedule should include all activities and milestones to take the Project from schematic design to occupancy. Scheduled activities will include meetings, design and construction document time frames, procurement delivery dates, permitting, approvals of authorities, coordination time frames and construction dates.
5.1.3 Contractor shall provide budget development and cost evaluation consisting of estimating, value analysis and life cycle analysis. Estimates shall be prepared at schematic design and design development. Interim estimate revisions estimates shall be prepared any time there is a significant design change. Proposed systems shall be evaluated for first cost, constructability, annual maintenance costs, annual utility costs, life expectancy and schedule impact.
Appears in 2 contracts
Sources: Construction Management Contract, Construction Management Contract