Common use of Outage Authority and Coordination Clause in Contracts

Outage Authority and Coordination. Interconnection Customer and Transmission Owner may each in accordance with Good Utility Practice in coordination with the other Party and Transmission Provider remove from service any of its respective Interconnection Facilities, System Protection Facilities, Network Upgrades, System Protection Facilities or Distribution Upgrades that may impact the other Party’s facilities as necessary to perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a removal of such facility(ies) from service will use Reasonable Efforts to notify one another and schedule such removal on a date and time mutually acceptable to the Parties. In all circumstances, any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Parties of such removal.

Appears in 5 contracts

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.), Generator Interconnection Agreement, Generator Interconnection (ITC Holdings Corp.)

AutoNDA by SimpleDocs

Outage Authority and Coordination. Interconnection Customer and Transmission Owner may each in In accordance with Good Utility Practice and in coordination with the other Party and Transmission Provider Party, the Interconnection Customer may remove from service any of its respective the Interconnection Customer’s Interconnection Facilities, System Protection Facilities, Network Upgrades, System Protection and the Transmission Provider may remove the Transmission Provider’s Interconnection Facilities or Distribution Upgrades any part of the Transmission System, from service that may impact the other Party’s 's facilities as necessary to perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a removal of such facility(ies) from service will use Reasonable Efforts to notify one another and schedule such removal on a date and time mutually acceptable to the Parties. In all circumstances, circumstances any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Parties Party of such removal. Neither Party shall be liable to the other for damages of any kind in connection with any such outage.

Appears in 5 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Outage Authority and Coordination. Interconnection Customer and Transmission Owner may each in accordance with Good Utility Practice in coordination with the other Party and Transmission Provider remove from service any of its respective Interconnection Facilities, System Protection Facilities, Network Upgrades, System Protection Facilities or Distribution Upgrades that may impact the other Party’s 's facilities as necessary to perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a removal of such facility(ies) from service will use Reasonable Efforts to notify one another and schedule such removal on a date and time mutually acceptable to the Parties. In all circumstances, any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Parties of such removal.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.), Asset Sale Agreement (CMS Energy Corp)

AutoNDA by SimpleDocs

Outage Authority and Coordination. Interconnection Customer Each Party mayDeveloper and Transmission Owner may each each, in accordance with NYISO procedures and Good Utility Practice and in coordination with the other Party and Transmission Provider Party, remove from service any of its respective Interconnection Facilities, System Protection Facilities, Network Upgrades, System Protection InterconnectionAttachment Facilities or Distribution Upgrades Network UpgradesSystem Upgrade Facilities that may impact the other Party’s facilities as necessary to perform maintenance or testing or to install or replace equipment. Absent an Emergency ConditionConditionState , the Party scheduling a removal of such facility(ies) from service will use Reasonable Efforts to notify one another and schedule such removal on a date and time mutually acceptable to the Parties. In all circumstances, any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Parties of such removal.both Partiesthe

Appears in 1 contract

Samples: Interconnection Agreement