Common use of No Damages for Delay Clause in Contracts

No Damages for Delay. The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

Appears in 41 contracts

Sources: Construction Management Agreement, Construction Management Agreement, Design Build Contract

No Damages for Delay. The Contractor has no claim for monetary damages for delay or hindrances to the Work work from any cause, including without limitation any act or omission of the Owner.

Appears in 7 contracts

Sources: General Construction Services Contract, Job Order, General Construction Services Contract

No Damages for Delay. The Contractor has no claim for monetary damages for delay or hindrances to the Work work from any cause, including without limitation any act or omission of the Owner.. An extension of the

Appears in 6 contracts

Sources: Design/Build Agreement, Construction Contract, Construction Contract

No Damages for Delay. The Contractor has no claim for monetary damages for delay or hindrances to the Work work from any cause, including without limitation any act or omission of the OwnerCity.

Appears in 1 contract

Sources: Design Build Services Agreement

No Damages for Delay. The Contractor has no claim for monetary damages for delay or hindrances to the Work work from any cause, including without limitation any act or omission of the Owner.

Appears in 1 contract

Sources: Contract