No Damages for Delay Sample Clauses

No Damages for Delay. The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.
AutoNDA by SimpleDocs
No Damages for Delay. An extension of the Contract Time shall be the sole remedy of Contractor for delays in performance of the Work, whether or not such delays are foreseeable, except for delays caused solely by acts of Owner that constitute intentional interference with Contractor’s performance of the Work and then only to the extent such acts continue after Contractor notifies Owner in writing of such interference. For delays caused by any act(s) other than the sole intentional interference of Owner, Contractor shall not be entitled to any compensation or recovery of any damages including, without limitation, consequential damages, lost opportunity costs, impact damages, loss of productivity, or other similar damages. Owner’s exercise of any of its rights or remedies under the Contract including, without limitation, ordering changes in the Work or directing suspension, rescheduling, or correction of the Work, shall not be construed as intentional interference with Contractor’s performance of the Work regardless of the extent or frequency of Owner’s exercise of such rights or remedies.
No Damages for Delay. Neither you nor your agents, employees, and subcontractors are entitled to any damages from the City, nor is any party entitled to be reimbursed by the City, for damages, charges or other losses or expenses incurred by you by reason of delays or hindrances in the performance of the Services, whether or not caused by the City. On notice to the City of a delay outside your control, you may request additional time to complete your performance. The decision to grant additional time is in the sole and absolute discretion of the City.
No Damages for Delay. During the Term, Company is not entitled to and must make no charges or claims for damages for any delays or hindrances from any cause in connection with the Services. If Company’s performance of the Services is delayed by causes beyond Company’s reasonable control, at the Institution’s sole option, the Institution may either terminate this Agreement or extend the time to complete the Services to reflect the extent of the delay (if extension is feasible given the project deadlines and the expectations of public performance), provided the Company has given the Institution written notice within ten days after delay begins. The notice by the Company must include a description of the reasons for the delay and the steps Company has taken or will take to mitigate the effects of the delay.
No Damages for Delay. In no event shall CCI be liable to Contractor for any damages or increased compensation of any kind for any delay or disruption to Contractor’s performance of Work regardless of whether such delay is caused by CCI, or by other parties under CCI’s control, or by Force Majeure, or by any other cause.
No Damages for Delay. Due to the unique requirements of working within a public facility which may be shared with other user-groups and adjacent to other public facilities, Owner may, at any time, restrict the Work to non-disruptive activities to reduce noise, vibration, air pollution, or any other nuisance, intrusion, or danger affecting adjacent public functions and duties. In each case, Owner will make a good faith effort to provide sufficient advanced notice of restriction to Contractor; and, Contractor shall make a good faith effort to reallocate activities, materials, and forces onsite to avoid delay to the project schedule. Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including, without limitation, any act or omission of Owner.
No Damages for Delay. The Contractor agrees that it, its members, if a partnership or joint venture and its Subcontractors shall make no claims against the City for damages, charges, additional costs or hourly fees for costs incurred by reason of delays or hindrances by the City in the performance of its obligations under this Agreement.
AutoNDA by SimpleDocs
No Damages for Delay. No claim for damages or any claim, other than for an extension of time, shall be made or asserted against County by reason of any delay. Contractor shall not be entitled to an increase in the GMP or payment or compensation of any kind from County for direct, indirect, general conditions, consequential, impact or other costs, expenses or damages, including, but not limited to, costs of acceleration or inefficiency, arising because of delay, disruption, interference or hindrance from any cause whatsoever, whether such delay, disruption, interference or hindrance be reasonable or unreasonable, foreseeable or unforeseeable, or avoidable or unavoidable; provided, however, that this provision shall not preclude recovery of damages by Contractor for hindrances or delays due solely to fraud, bad faith, or active interference on the part of County or Consultant. Otherwise, Contractor shall be entitled only to extensions of the Contract Time as the sole and exclusive remedy for such resulting delay, in accordance with and to the extent specifically provided above.
No Damages for Delay. In the event of any delay as set forth in Section (b) herein, the Contractor may be entitled to an extension of the Contract Time only, and shall not be entitled to any additional payment on account of such delay. Without limiting the foregoing, except as otherwise specifically provided under Article 29, the Contractor shall not be entitled to payment or compensation of any kind from the Owner for direct, indirect or impact damages, including but not limited to costs of acceleration or extended home office overhead arising because of hindrance or delay from any cause whatsoever, whether such hindrances or delays be reasonable or unreasonable, foreseeable or unforeseeable, or avoidable or unavoidable. General Conditions
No Damages for Delay. Apart from a written extension of time, no payment, compensation, or adjustment of any kind shall be made to Independent Contractor for damages because of hindrances or delays in the progress of the work from any cause, and Independent Contractor agrees to accept in full satisfaction of such hindrances and delays any extension of time that the City of Nashua may provide.