Monthly Progress Payments. 6.2.1 On or before the date established in the Agreement, Design-Builder shall submit for Owner's review and approval its Application for Payment requesting payment for all Work performed as of the date of the Application for Payment. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required by Section 2.1.4 hereof. 6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that (i) Owner is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location, (ii) the equipment and materials are protected by suitable insurance and (iii) upon payment, Owner will receive the equipment and materials free and clear of all liens and encumbrances. 6.2.3 The Application for Payment shall constitute Design-Builder's representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Owner free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project, or upon Design-Builder's receipt of payment, whichever occurs earlier.
Appears in 2 contracts
Sources: Standard Form of Agreement Between Owner and Design Builder (Lump Sum) (Little Sioux Corn Processors LLC), Standard Form of Agreement Between Owner and Design Builder (Lump Sum) (Little Sioux Corn Processors LLC)
Monthly Progress Payments. 6.2.1 On or before the date established in the Agreement, Design-Builder shall submit for Owner's ’s review and approval its Application for Payment requesting payment for all Work performed as of the date of the Application for Payment. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required by Section 2.1.4 hereof.
6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that (i) Owner is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location, (ii) the equipment and materials are protected by suitable insurance and (iii) upon payment, Owner will receive the equipment and materials free and clear of all liens and encumbrances; (iv) equipment/materials are in accordance with the approved plans and specifications.
6.2.3 The Application for Payment shall constitute Design-Builder's ’s representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Owner free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project, or upon Design-Builder's ’s receipt of payment, whichever occurs earlier.
6.2.4 Progress payments shall be made by the Owner to the Design-Builder within fifteen (15) business days (Monday through Friday excluding City Holidays) following receipt of invoice.
Appears in 2 contracts
Sources: Design Build Contract, Design Build Contract
Monthly Progress Payments. 6.2.1 On or before the date established in the Agreement, Design-Builder shall submit for Owner's ’s review and approval its Application for Payment requesting payment for all Work performed as of the date of the Application for Payment. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required by Section 2.1.4 hereof.
6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that (i) Owner is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location, (ii) the equipment and materials are protected by suitable insurance and (iii) upon payment, Owner will receive the equipment and materials free and clear of all liens and encumbrances.
6.2.3 All discounts offered by Subcontractor, Sub-Subcontractors and suppliers to Design- Builder for early payment shall accrue one hundred percent to Design-Builder to the extent Design-Builder advances payment. Unless Owner advances payment to Design-Builder specifically to receive the discount, Design-Builder may include in its Application for Payment the full undiscounted cost of the item for which payment is sought.
6.2.4 The Application for Payment shall constitute Design-Builder's ’s representation that the Work described herein has been performed consistent with the Contract Documents, that all subconsultants, subcontractors, and suppliers have been paid, less applicable earned retainage in accordance with RCW 60.28.011, as their interests appeared in the last preceding Application for Payment, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Owner free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project, or upon Design-Builder's ’s receipt of payment, whichever occurs earlier.
Appears in 1 contract
Monthly Progress Payments. 6.2.1 On or before the date established in the Agreement, Design-Builder shall submit for Owner's ’s review and approval its Application for Payment requesting payment for all Work performed as of the date of the Application for Payment. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required by Section 2.1.4 hereof. Items to be invoiced based on lump sums or fixed unit prices may be invoiced according to agreed progress of the Work. Items invoiced to be included in the Cost of the Work shall be supported by specific documentation justifying the cost of such items.
6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that (i) Owner is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location, (ii) the equipment and materials are protected by suitable insurance and (iii) upon payment, Owner will receive the equipment and materials free and clear of all liens and encumbrances.
6.2.3 The Application for Payment shall constitute Design-Builder's ’s representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Owner free and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project, or upon Design-Builder's ’s receipt of payment, whichever occurs earlier.
6.2.4 Based on site inspections and Work progress review, Design Consultant will verify that the invoiced progress of the Work is accurately reflected, meets the quality requirements of the Contract Documents, and is in accordance with the design plans and specifications issued for construction of the Work.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Design Builder