Common use of Maintenance obligations of the Contractor Clause in Contracts

Maintenance obligations of the Contractor. 14.1.1 The Contractor shall maintain the Project Highway for a period of [2 (two) years] commencing from the date of the Provisional Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid a total amount equal to 1.5% (one and one-half per cent) of the Contract Price for the first year of maintenance, and 2% (two per cent) of the Contract Price for the second year of maintenance, inclusive of all taxes. The amount payable for maintenance shall be adjusted to reflect any increase or decrease arising out of variation in WPI to be determined in accordance with the provisions of Clause 19.12. For the avoidance of doubt, it is agreed that in the event no Provisional Certificate is issued, the Maintenance Period shall commence from the date of the Completion Certificate. It is further agreed that the Contract Price hereunder shall be reckoned with reference to the amount specified in Clause 19.1.1, which shall be adjusted to the extent of Change of Scope and the works withdrawn under the provisions of Clause 8.3.3, but shall not include any price adjustments in pursuance of Clause 19.10.

Appears in 2 contracts

Samples: Construction) Agreement, Construction) Agreement

AutoNDA by SimpleDocs

Maintenance obligations of the Contractor. 14.1.1 The Contractor shall maintain the Project Highway for a period of [2 5 (twofive) years] years commencing from the date of the Provisional Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor contractor shall be paid a total amount equal to 1.50.5% (one and one-half per cent) of the Contract Price for the first year of maintenanceand 0.5%, and 21%, 1 %, 1.5% (two per cent) of the Contract Price for the second second, third, fourth and fifth year respectively in case of maintenance, inclusive of all taxesroad projects. The amount payable for maintenance shall be adjusted to reflect any increase or decrease arising out of variation in WPI to be determined in accordance with the provisions of Clause 19.12. For the avoidance of doubt, it is agreed that in the event no Provisional Certificate is issued, the Maintenance Period shall commence from the date of the Completion Certificate. It is further agreed that the Contract Price hereunder shall be reckoned with reference to the amount specified in Clause 19.1.1, which shall be adjusted to the extent of Change of Scope and the works withdrawn under the provisions of Clause 8.3.3, but shall not include any price adjustments in pursuance of Clause 19.10...

Appears in 1 contract

Samples: Procurement and Construction Agreement

Maintenance obligations of the Contractor. 14.1.1 The Contractor shall maintain the Project Highway Works for a period of [2 (two) years] commencing from the date of the Provisional Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid a total amount equal to 1.51% (one and one-half per cent) of the Contract Price for the first year of maintenance, and 21% (two one per cent) of the Contract Price for the second year of maintenance, inclusive of all taxes. The amount payable for maintenance shall be adjusted to reflect any increase or decrease arising out of variation in WPI to be determined in accordance with the provisions of Clause 19.12. For the avoidance of doubt, it is agreed that in the event no Provisional Certificate is issued, the Maintenance Period shall commence from the date of the Completion Certificate. It is further agreed that the Contract Price hereunder shall be reckoned with reference to the amount specified in Clause 19.1.1, which shall be adjusted to the extent of Change of Scope and the works withdrawn under the provisions of Clause 8.3.3, but shall not include any price adjustments in pursuance of Clause 19.10Scope.

Appears in 1 contract

Samples: Procurement and Construction Agreement

Maintenance obligations of the Contractor. 14.1.1 The Contractor shall maintain the Project Highway for a period of [2 5 (twofive) years] years commencing from the date of the Provisional Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor contractor shall be paid a total amount equal to 1.50.5% (one and one-half per cent) of the Contract Price for the first first year of maintenanceand 0.5%, and 21%, 1 %, 1.5% (two per cent) of the Contract Price for the second second, third, fourth and fifth year respectively in case of maintenance, inclusive of all taxesroad projects. The amount payable for maintenance shall be adjusted to reflect any increase or decrease arising out of variation in WPI to be determined in accordance with the provisions of Clause 19.12. For the avoidance of doubt, it is agreed that in the event no Provisional Certificate is issued, the Maintenance Period shall commence from the date of the Completion Certificate. It is further agreed that the Contract Price hereunder shall be reckoned with reference to the amount specified in Clause 19.1.1, which shall be adjusted to the extent of Change of Scope and the works withdrawn under the provisions of Clause 8.3.3, but shall not include any price adjustments in pursuance of Clause 19.10...

Appears in 1 contract

Samples: Procurement and Construction Agreement

AutoNDA by SimpleDocs

Maintenance obligations of the Contractor. 14.1.1 The Contractor shall maintain the Project Highway PROJECT for a period of [2 4 (twofour) years] years commencing from the date of the Provisional Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid a total amount equal to 1.50.5% (one and one-half per cent) of the Contract Price for the first year of maintenanceand 1%, 1.5% and 2% (two per cent) of the Contract Price for the second second, third and fourth year of maintenancerespectively Amount shall be, inclusive of all taxes. The amount payable for maintenance shall be adjusted to reflect any increase or decrease arising out of variation in WPI to be determined in accordance with the provisions of Clause 19.12. For the avoidance of doubt, it is agreed that in the event no Provisional Certificate is issued, the Maintenance Period shall commence from the date of the Completion Certificate. It is further agreed that the Contract Price hereunder shall be reckoned with reference to the amount specified in Clause 19.1.1, which shall be adjusted to the extent of Change of Scope and the works withdrawn under the provisions of Clause 8.3.3, but shall not include any price adjustments in pursuance of Clause 19.10.

Appears in 1 contract

Samples: Engineering Procurement And

Maintenance obligations of the Contractor. 14.1.1 The Contractor shall maintain the Project Highway Works carried out by the contractor for a period of [2 4 (twofour) years] years commencing from the date of the Provisional Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid a total amount equal to 1.51% (one and one-half per cent) of the Contract Price for the first year of maintenance, and 21.5% (two one and half per cent) of the Contract Price for the second Second, Third and Fourth year of maintenance, inclusive of all taxes. .. The amount payable for maintenance shall be adjusted to reflect any increase or decrease arising out of variation in WPI to be determined in accordance with the provisions of Clause 19.12. For the avoidance of doubt, it is agreed that in the event no Provisional Certificate is issued, the Maintenance Period shall commence from the date of the Completion Certificate. It is further agreed that the Contract Price hereunder shall be reckoned with reference to the amount specified in Clause 19.1.1, which shall be adjusted to the extent of Change of Scope and the works withdrawn under the provisions of Clause 8.3.3, but shall not include any price adjustments in pursuance of Clause 19.10.

Appears in 1 contract

Samples: Contract Agreement for Design and Construction