Tests on Completion Sample Clauses

Tests on Completion. (i) At least 30 (thirty) days prior to the likely completion of the Project Highway, or a Section thereof, the Contractor shall notify the Authority’s Engineer of its intent to subject the Project Highway or a Section thereof, to Tests. The date and time of each of the Tests shall be determined by the Authority’s Engineer in consultation with the Contractor, and notified to the Authority who may designate its representative to witness the Tests. The Contractor shall either conduct the Tests as directed by the Authority’s Engineer or provide such assistance as the Authority’s Engineer may reasonably require for conducting the Tests. In the event of the Contractor and the Authority’s Engineer failing to mutually agree on the dates for conducting the Tests, the Contractor shall fix the dates by giving not less than 10 (ten) days’ notice to the Authority’s Engineer.
AutoNDA by SimpleDocs
Tests on Completion. 12.1.1 No later than 30 (thirty) days prior to the likely completion of the Project or a part thereof, the Contractor shall prepare and submit to the Authority Engineer the documents required for seeking approval of the Commissioner of Railway Safety in accordance with the provisions of the [Railways Opening for Public Carriage of Passenger Rules, the Indian Railway Permanent Way Manual, the Indian Railways Manual of A.C. Traction ]as the case may be, and notify the Authority Engineer of its intent to subject the Project to Tests, if required. After ensuring and procuring that the documents required to be submitted to the Commissioner for Railway Safety meet the requirements of Applicable Laws, the Authority Engineer shall, in consultation with the Contractor, determine the date and time of each of the Tests, and inform the Authority who may designate its representative to witness the Tests. The Contractor shall provide such assistance as the Authority Engineer may reasonably require for conducting the Tests. For avoidance of doubts, the parties agree that in the event of the Contractor and the Authority Engineer failing to mutually agree on the dates for conducting the Tests, the Contractor shall fix the dates by giving not less than10 (ten) days’ notice to the Authority Engineer.Authority will carry outtests on completion within 30 days of receiving request from Contractor.And if Authority Engineer fails to carry out test within 30 days, the Authority will pay damage to Contractor @ 0.02% of the payment pending for want of test per day.
Tests on Completion. 12.1.1 No later than 30 (thirty) days prior to the likely completion of the Railway Project or a part thereof, the Contractor shall prepare and submit to the Authority Engineer the documents required for seeking approval of the Commissioner of Railway Safety in accordance with the provisions of the Railways Opening for Public Carriage of Passenger Rules, the Indian Railway Permanent Way Manual, the Indian Railways Manual of AC Traction, Indian Railways Signal Engineering Manual, Indian Railways Telecom Manual as the case may be, and notify the Authority Engineer of its intent to subject the Railway Project to Tests. After ensuring and procuring that the documents required to be submitted to the Commissioner for Railway Safety meet the requirements of Applicable Laws, the Authority Engineer shall, in consultation with the Contractor, determine the date and time of each of the Tests, and inform the Authority who may designate its representative to witness the Tests. The Contractor shall provide such assistance as the Authority Engineer may reasonably require for conducting the Tests. For avoidance of doubts, the parties agree that in the event of the Contractor and the Authority Engineer failing to mutually agree on the dates for conducting the Tests, the Contractor shall fix the dates by giving not less than 10 (ten) days’ notice to the Authority Engineer. Authority will carry out tests on completion within 30 days of receiving request from contractor. And if Authority Engineer fails to carry out test within 30 days, the Authority will pay damage to Contractor @ 0.02% of the payment pending for want of test per day.
Tests on Completion. “Tests on Completion” means the tests specified in the Contract or otherwise agreed by the Engineer and the Contractor which are to be made by the Contractor before the Works or any Section or part thereof are taken over by the Employer.
Tests on Completion. 1.1.4.5 Final Statement 1.1.3.3
Tests on Completion a. Before commencement of the Tests, the Concessionaire shall ensure that it has provided the Authority with all required documents under Articles 8.6,
Tests on Completion. 12.1.1 At least 30 (thirty) days prior to the likely completion of the Project Works, the Contractor shall notify the Employer’s Engineer of its intent to subject the Project Works or a Section/ or any part thereof, to Tests. The date and time of each of the Tests shall be determined by the Employer’s Engineer in consultation with the Contractor, and notified to the Employer who may designate its representative to witness the Tests. The Contractor shall either conduct the Tests as directed by the Employer’s Engineer or provide such assistance as the Employer’s Engineer may reasonably require for conducting the Tests. In the event of the Contractor and the Employer’s Engineer failing to mutually agree on the dates for conducting the Tests, the Contractor shall fix the dates by giving not less than 10 (ten) days’ notice to the Employer’s Engineer.
AutoNDA by SimpleDocs
Tests on Completion. 9.1 Contractor’s obligations Delete first paragraph of Sub-Clause 9.1, and substitute: The Contractor shall carry out the Tests on Completion in accordance with this Clause, and Sub-Clause 7.4 [Testing] and the H1 - Technical Specifications and drawings [chapter Testing & Acceptance], after providing the documents in accordance with Sub-Clause 5.6 [As-Built Documents] and Sub-Clause 5.7 [Operation and Maintenance Manuals].
Tests on Completion. 12.1.1 At least 30 (thirty) days prior to the likely completion of the Project Works, or a Section or any Part thereof, the Contractor shall notify the Employer's Engineer of its intent to subject the Project Works or a Section/ or any part thereof, to Tests. The date and time of each of the Tests shall be determined by the Employer's Engineer in consultation with the Contractor, and notified to the Employer who may designate its representative to witness the Tests. The Contractor shall either conduct the Tests as directed by the Employer's Engineer or provide such assistance as the Employer's Engineer may reasonably require for conducting the Tests. In the event of the Contractor and the Employer's Engineer failing to mutually agree on the dates for conducting the Tests, the Contractor shall fix the dates by giving not less than 10 (ten) days' notice to the Employer's Engineer.
Tests on Completion a. Before commencement of the Tests, the Concessionaire shall ensure that it has provided the Authority with all required documents under Articles 8.6, 8.7 and 8.8. The provisions of Article 11.3 shall be applicable mutatis mutandis to the carrying out of the Tests under this Article. The Concessionaire shall give to Authority and the Independent Engineer not less than 28 (twenty eight) days ' notice of its intent to carry out the Tests. Unless otherwise agreed, such Tests shall be carried out within 14 (fourteen) days after this date, or on such day or days as the Independent Engineer shall instruct.