Common use of Maintenance obligations of the Contractor Clause in Contracts

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):

Appears in 18 contracts

Samples: Contract Agreement, Contract Agreement, Draft Contract Agreement

AutoNDA by SimpleDocs

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of [5 (five) / 10 (ten)] years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 17 contracts

Samples: Draft Contract Agreement, morth.nic.in, nhidcl.com

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 7 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H-H):

Appears in 3 contracts

Samples: Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 [10 (five) ten)] years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 3 contracts

Samples: data.opencity.in, data-opencity.sgp1.cdn.digitaloceanspaces.com, data-opencity.sgp1.cdn.digitaloceanspaces.com

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of [5 (five) / 10 (ten)] years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the "Maintenance Period"). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 10 (fiveten) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):

Appears in 1 contract

Samples: Draft Contract Agreement

AutoNDA by SimpleDocs

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of [5 (five) / 10 (ten)] years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance Mainte- xxxxx obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 1 contract

Samples: Draft Contract Agreement

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five4(four) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 1 contract

Samples: Construction Agreement

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 (five) / 10 (ten) years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 1 contract

Samples: nhidcl.com

Maintenance obligations of the Contractor. (i) The Contractor shall maintain the Project Highway for a period of 5 [05 (five) )] years, corresponding to the Defects Liability Period, commencing from the date of the Completion Certificate (the “Maintenance Period”). For the performance of its Maintenance obligations, the Contractor shall be paid (if not included in the Schedule - H):paid:

Appears in 1 contract

Samples: nhidcl.com