Common use of Interconnection System Reliability Impact Study Procedures Clause in Contracts

Interconnection System Reliability Impact Study Procedures. The NYISO shall coordinate the SRIS with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the receipt of the fully executed Interconnection System Reliability Impact Study Agreement, study deposit, and technical data. If NYISO uses Clustering, the NYISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO Operating Committee shall approve each final SRIS. At the request of the Developer or at any time the NYISO determines that it will not meet the required time frame for completing the SRIS, NYISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO is unable to complete the SRIS within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO shall provide the Developer all supporting documentation, workpapers and relevant pre-Interconnection Request and post-Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 4 contracts

Samples: nyisoviewer.etariff.biz, nyisoviewer.etariff.biz, nyisoviewer.etariff.biz

AutoNDA by SimpleDocs

Interconnection System Reliability Impact Study Procedures. The NYISO shall coordinate the SRIS Interconnection System Reliability Impact Study with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the receipt of the fully executed Interconnection System Reliability Impact Study Agreement, study depositpayment, and technical data. If NYISO uses Clustering, the NYISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO Operating Committee shall approve each final SRISInterconnection System Reliability Impact Study. At the request of the Developer or at any time the NYISO determines that it will not meet the required time frame for completing the SRISInterconnection System Reliability Impact Study, NYISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO is unable to complete the SRIS Interconnection System Reliability Impact Study within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO shall provide the Developer all supporting documentation, workpapers and relevant pre-Interconnection Request and post-Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 4 contracts

Samples: nyisoviewer.etariff.biz, nyisoviewer.etariff.biz, nyisoviewer.etariff.biz

Interconnection System Reliability Impact Study Procedures. The NYISO shall coordinate the SRIS with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the receipt of the fully executed Interconnection System Reliability Impact Study Agreement, study deposit, and technical data. If NYISO uses Clustering, the NYISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO Operating Committee shall approve each final SRIS. At the request of the Developer or at any time the NYISO determines that it will not meet the required time frame for completing the SRIS, NYISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO is unable to complete the SRIS within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO shall provide the Developer all supporting documentation, workpapers and relevant pre-pre- Interconnection Request and post-Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 3 contracts

Samples: nyisoviewer.etariff.biz, nyisoviewer.etariff.biz, nyisoviewer.etariff.biz

Interconnection System Reliability Impact Study Procedures. The NYISO ISO shall coordinate the SRIS with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO ISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO ISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the ISO confirms receipt of the fully executed Interconnection System Reliability Impact Study Agreement, required study deposit, and required technical data, and Site Control (if Site Control was not provided with the Interconnection Request), . If NYISO ISO uses Clustering, the NYISO ISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO ISO Operating Committee shall approve each final SRIS. At the request of the Developer or at any time the NYISO ISO determines that it will not meet the required time frame timeframe for completing the SRIS, NYISO the ISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO ISO is unable to complete the SRIS within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO ISO shall provide the Developer all supporting documentation, workpapers and relevant pre-Interconnection Request and post-post- Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 2 contracts

Samples: Service Agreement, nyisoviewer.etariff.biz

Interconnection System Reliability Impact Study Procedures. The NYISO shall coordinate the SRIS Interconnection System Reliability Impact Study with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the receipt of the fully executed Interconnection System Reliability Impact Study Agreement, study depositpayment, and technical data. If NYISO uses Clustering, the NYISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO Operating Committee shall approve each final SRISInterconnection System Reliability Impact Study. At the request of the Developer or at any time the NYISO determines that it will not meet the required time frame for completing the SRISInterconnection System Reliability Impact Study, NYISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO is unable to complete the SRIS Interconnection System Reliability Impact Study within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO shall provide the Developer all supporting documentation, workpapers and relevant pre-Interconnection Request and post-post- Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 1 contract

Samples: nyisoviewer.etariff.biz

AutoNDA by SimpleDocs

Interconnection System Reliability Impact Study Procedures. The NYISO shall coordinate the SRIS Interconnection System Reliability Impact StudySRIS with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the receipt of the fully executed Interconnection System Reliability Impact Study Agreement, study depositpaymentdeposit, and technical data. If NYISO uses Clustering, the NYISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO Operating Committee shall approve each final SRISInterconnection System Reliability Impact StudySRIS. At the request of the Developer or at any time the NYISO determines that it will not meet the required time frame for completing the SRISInterconnection System Reliability Impact StudySRIS, NYISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO is unable to complete the SRIS Interconnection System Reliability Impact StudySRIS within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO shall provide the Developer all supporting documentation, workpapers and relevant pre-pre- Interconnection Request and post-Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 1 contract

Samples: nyisoviewer.etariff.biz

Interconnection System Reliability Impact Study Procedures. The NYISO ISO shall coordinate the SRIS with any Affected System that is affected by the Interconnection Request pursuant to Section 30.3.5 above. The NYISO ISO shall utilize existing studies to the extent practicable when it performs the study. The NYISO ISO shall use Reasonable Efforts to complete the SRIS within ninety (90) Calendar Days after the ISO confirms receipt of the fully executed Interconnection System Reliability Impact Study Agreement, required study deposit, and required technical data, and Site Control (if Site Control was not provided with the Interconnection Request); provided, however, if the SRIS requires a deliverability evaluation pursuant to Section 30.7.3.2 of this Attachment X, the ISO shall use Reasonable Efforts to complete the SRIS within 120 Calendar Days after the ISO confirms receipt of the required study deposit, required technical data, and Site Control (if Site Control was not provided with the Interconnection Request). If NYISO ISO uses Clustering, the NYISO ISO shall use Reasonable Efforts to deliver a completed SRIS within ninety (90) Calendar Days after the close of the Queue Cluster Window. The NYISO ISO Operating Committee shall approve each final SRIS. At the request of the Developer or at any time the NYISO ISO determines that it will not meet the required time frame timeframe for completing the SRIS, NYISO the ISO shall notify the Developer as to the schedule status of the SRIS. If the NYISO ISO is unable to complete the SRIS within the time period, it shall notify the Developer and provide an estimated completion date with an explanation of the reasons why additional time is required. Upon request, the NYISO ISO shall provide the Developer all supporting documentation, workpapers and relevant pre-Interconnection Request and post-Interconnection Request power flow, short circuit and stability databases for the SRIS, subject to confidentiality arrangements consistent with Section 30.13.1.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement