Guaranteed Final Completion Date Clause Samples
POPULAR SAMPLE Copied 1 times
Guaranteed Final Completion Date. Contractor shall achieve Final Completion of the Work no later than one hundred eighty (180) Days after achieving Substantial Completion (“Guaranteed Final Completion Date”). The Guaranteed Final Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Final Completion Date. Seller shall achieve Final Completion within 120 Days after the Substantial Completion Date. After Final Completion has been achieved, NorthWestern shall issue to Seller a certificate of final completion in a form mutually agreed by the Parties (“Certificate of Final Completion”).
Guaranteed Final Completion Date. The date which is 645 days after the Starting Date, subject to extension in accordance with the terms of this Agreement, by which date Contractor has committed to achieve Final Completion.
Guaranteed Final Completion Date. The Guaranteed Final Completion Date for Subproject #1 shall be September 1, 2010. The Guaranteed Final Completion Date for Subproject #2 shall be October 31, 2010. The Guaranteed Final Completion Date for Subproject #3 shall be November 15, 2010.
Guaranteed Final Completion Date. The date "July 31, 1998" set forth in the first and sixth lines of the definition of "Guaranteed Final Completion Date" in Article 2 of the Agreement is hereby changed to "November 30, 1998."