Formation of Implementation Plan. 6.1.1 Where an Implementation Plan has not been agreed and included in Contract Schedule 4 (Implementation Plan) on the Contract Commencement Date, but the Customer has specified in the Contract Order Form that the Supplier shall provide a draft Implementation Plan prior to the commencement of the provision of the Goods and/or Services, the Suppliers draft must contain information at the level of detail necessary to manage the implementation stage effectively and as the Customer may require. The draft Implementation Plan shall take account of all dependencies known to, or which should reasonably be known to, the Supplier.
Appears in 2 contracts
Samples: www.contractsfinder.service.gov.uk, Dynamic Purchasing System Agreement
Formation of Implementation Plan. 6.1.1 Where the Parties agreed in the Order Form (or elsewhere in this Call Off Contract) that an Implementation Plan has not been agreed and included (or parts thereof) shall be provided in Contract Schedule 4 (Implementation Plan) on the Contract Commencement Date, but the Customer has specified in the Contract Order Form that draft by the Supplier shall provide a draft Implementation Plan prior to the commencement of the provision of the supply of the Goods and/or and the Services, the Suppliers Supplier’s draft must contain information at the level of detail necessary to manage the implementation stage effectively and as the Customer may require. The draft Implementation Plan shall take account of all dependencies known to, or which should reasonably be known to, to the Supplier.
Appears in 1 contract
Samples: Model Contract
Formation of Implementation Plan. 6.1.1 Where an Implementation Plan has not been agreed and included in Contract Call Off Schedule 4 (Implementation Plan) on the Contract Call Off Commencement Date, but the Customer Contracting Authority has specified in the Contract Call Off Order Form that the Supplier shall provide a draft Implementation Plan prior to the commencement of the provision of the Goods and/or Services, the Suppliers Supplier’s draft must contain information at the level of detail necessary to manage the implementation stage effectively and as the Customer Contracting Authority may require. The draft Implementation Plan shall take account of all dependencies known to, or which should reasonably be known to, the Supplier.
Appears in 1 contract
Samples: Framework Agreement
Formation of Implementation Plan. 6.1.1 Where the Parties agreed in paragraph 2.7 of the Order Form (or elsewhere in this Call Off Contract) that an Implementation Plan has not been agreed and included (or parts thereof) shall be provided in Contract Schedule 4 (Implementation Plan) on the Contract Commencement Date, but the Customer has specified in the Contract Order Form that draft by the Supplier shall provide a draft Implementation Plan prior to the commencement of the provision of the Goods and/or Services, the Suppliers Supplier’s draft must contain information at the level of detail necessary to manage the implementation stage effectively and as the Customer may require. The draft Implementation Plan shall take account of all dependencies known to, or which should reasonably be known to, the Supplier.
Appears in 1 contract
Samples: Terms for Services