Common use of Force Account Clause in Contracts

Force Account. The Department will require the Contractor to proceed with additional work on a force account basis when neither the Department nor the Contractor can firmly establish an applicable estimate for the cost of the work because the scope of the work is not known; that is, the level of effort required to perform and complete the work is unknown or not quantifiable at the time of discovery or start of the extra work, and will be determined as work progresses. The rates for labor, equipment and materials to be used in cases of work performed on a force account basis will be compensated in the following manner:

Appears in 21 contracts