Common use of EXTENSION OF TIME FOR PERFORMANCE Clause in Contracts

EXTENSION OF TIME FOR PERFORMANCE. 13.1 If performance by the Contractor is delayed for a reason set forth in Article 13.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules.

Appears in 11 contracts

Samples: Construction Contract, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

EXTENSION OF TIME FOR PERFORMANCE. 13.1 41.1. If performance by the Contractor is delayed for a reason set forth in Article 13.341.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules.

Appears in 11 contracts

Samples: Supply and Service Agreement, And Supply and Service Agreement, Supply and Service Agreement

EXTENSION OF TIME FOR PERFORMANCE. 13.1 13.1. If performance by the Contractor is delayed for a reason set forth in Article 13.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules.

Appears in 10 contracts

Samples: Supply and Service Agreement, Supply and Service Agreement, a856-cityrecord.nyc.gov

EXTENSION OF TIME FOR PERFORMANCE. 13.1 46.1. If performance by the Contractor is delayed for a reason set forth in Article 13.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 46 and the PPB Rules.

Appears in 10 contracts

Samples: Furnish and Install Agreement, Supply and Service Agreement, Supply and Service Agreement

EXTENSION OF TIME FOR PERFORMANCE. 13.1 46.1. If performance by the Contractor is delayed for a reason set forth in Article 13.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules.

Appears in 9 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

AutoNDA by SimpleDocs

EXTENSION OF TIME FOR PERFORMANCE. 13.1 41.1. If performance by the Contractor is delayed for a reason set forth in Article 13.341.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 46 and the PPB Rules.

Appears in 2 contracts

Samples: Supply and Service Agreement, Staten Island Ferry

EXTENSION OF TIME FOR PERFORMANCE. 13.1 47.1. If performance by the Contractor is delayed for a reason set forth in Article 13.347.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules.

Appears in 2 contracts

Samples: a856-cityrecord.nyc.gov, a856-cityrecord.nyc.gov

EXTENSION OF TIME FOR PERFORMANCE. 13.1 46.1. If performance by the Contractor is delayed for a reason set forth in Article 13.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and section 4-03(b) of the PPB Rules.

Appears in 1 contract

Samples: a856-cityrecord.nyc.gov