Extended Contract Times Sample Clauses

Extended Contract Times. Should the Contract Times to complete the Work be extended beyond the period identified in paragraph C4.01, payment for Engineer’s services shall be continued based on the Standard Hourly Rates Method of Payment.
AutoNDA by SimpleDocs
Extended Contract Times. Should the Contract Times to complete the Work be extended beyond the period stated in the Task Order, payment for Testing Firm's services shall be continued based on the Standard Hourly Rates Method of Payment.

Related to Extended Contract Times

  • Extended Contract Teachers whose regularly assigned service is required beyond 196 days will be paid at the rate of 1/196 of their annual contracted salary for each day of service. The principal/immediate supervisor may recommend a supplemental contract for the number of days for which their services are required.

  • Extended Contracts A. In the event the number of days in a MBU’s contract is extended, that MBU shall be paid at the daily rate of 1/207 of their scheduled salary per additional day. MBUs on an extended contract shall receive all holidays and benefits received by MBUs during the school year.

  • Contract Times A. Time of the Essence

  • Contract Time The period of time established for completion of the Project by the Contract Documents. Contract Time commences upon the date specified in the Proceed Order and ends upon the Material Completion and Occupancy Date, as it may be amended.

  • Project Time As defined herein, this is the time within which the Contractor shall complete all Work contracted for under this Contract as indicated in a fully authorized Service Work Order pursuant to the Service Work Order Process provision set forth in this Contract.

  • Recovery of Schedule Delays During Last Sixty Days of Contract Time At any time during the last sixty days of the Contract Time that the Design Professional finds that the Contractor is behind schedule per the Contract Time, as amended, the Design Professional shall notify the Contractor in writing. Within seven days of the date of the Design Professional's notice, the Contractor shall prepare and deliver to the Design Professional and Owner a written plan explaining how the Contractor intends to bring the Project back on schedule. The Contractor's plan must provide sufficient detail to allow the Design Professional and Owner to determine the proposal's feasibility.

  • Extended Coverage For Professional Liability Errors and Omissions coverage under Section 18.1.5, Contractor shall continue such coverage for at least five years beyond the expiration or termination of this Contract. The Retroactive Date must be shown and must be before the Effective Date or the beginning of work on the Contract, whichever is earlier. If coverage is canceled or non-renewed, and not replaced with another claims made policy form with a Retroactive Date prior to the Effective Date, Contractor must purchase “extended reporting” coverage for a minimum of five years after expiration or termination of the Contract, whichever is earlier.

  • Four Day Work Week Schedule i. When working under the four (4) day work week schedule, Employees shall be paid at double time (2x) the regular hourly rate for all hours worked in excess of the regular ten (10) hours per day Monday through Thursday.

  • Initial Contract Term The Initial Contract Term shall be for two years. The Initial Contract Term shall begin on October 1, 2021, or on the last date the Contract is signed by all Parties, whichever is later. The Contract shall expire on October 1, 2023, unless terminated earlier in accordance with the Special Contract Conditions or Additional Special Contract Conditions.

  • ADDITIONAL SPECIAL CONTRACT CONDITIONS A. Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following: