Engineering Design. A. In addition to any other engineering requirements specified in Attachment A or any other provision, Attachment or Schedule of the Agreement, the following services, Drawings and Specifications shall be prepared and provided by Contractor in accordance with Attachment B in respect of all engineering disciplines during engineering of the Project: 1. Completing the engineering design documents, as required, which were developed by Contractor prior to the Agreement Date; 2. Provide engineering support for procurement, transportation, construction, commissioning and assistance to start-up; 3. Performance of all detailed studies, checks and reviews, procedures, and adaptation of design in all disciplines accordingly; 4. Developing and revising drawings sufficient for procurement of Equipment, installation, construction, manufacture, fabrication, commissioning, start-up, testing, operation and maintenance of the Project; 5. Submission of documents for review and comment in accordance with Attachment B; 6. Lead, participate in and action results of technical reviews, including preparation and supply of all required documents for team members; 7. Evaluate and close technical inquiries; 8. Preparation of Equipment data sheets; 9. Preparation of engineering material requisitions and purchase requisitions, and amendments as necessary; 10. Technical evaluation for all major Contractor-Supplied Equipment; 11. Requisitions, and other technical documents and evaluations for the procurement of all necessary bulk material and Contractor-Supplied Equipment; 12. Development and implementation of a plan for witnessing of factory tests at Vendor’s shops for major Contractor-Supplied Equipment; 13. Drawings control, Vendor data and documentation control using a computer database and Contractor’s document control procedure; 14. Provide Vendor’s recommendations for operating spare parts and prepare final operating spare parts list; 15. Develop list of first fills and start-up consumables (including strainers and filters); 16. Development of technical documents for Subcontracts; 17. Provision of engineering support for procurement, construction and commissioning; 18. Preparation of mechanical catalogues and Vendor data books; 19. Provision of all Record As-Built Drawings and Specifications; 20. Drawings and packages required for tie-ins; 21. Development of Equipment lists, instrument index, line lists; 22. Maintenance documentation for all Contractor-Supplied Equipment provided; 23. Participate in comprehensive safety reviews for E-HAZOP/HAZID/HAZOP/SIL, as required by Owner. The reviews shall occur and E-HAZOP/HAZID/HAZOP/SIL action items shall be closed out before completion of detailed design. Third party facilitation, paid by Owner, will be used to conduct the review meetings. The following HAZOP/SIL items have been closed. Unless listed below, HAZOP/SIL/Alternate Design Workshop items are unresolved and are excluded: HAZOP Items resolved and incorporated (at EPC execution) [***] SIL Items resolved and incorporated (at EPC execution) [***] For greater clarity, Parties agree that E-HAZOP reviews will be conducted during execution, and, therefore, E-HAZOP items are unresolved and excluded from the scope; 24. Not used; 25. Support fire explosion risk analysis, which will be performed by third party hired by Owner; 26. Support QRA as required, which will be performed by a third party hired by Owner; and 27. Support independent flare system review audit during detailed design – Contractor will be required to provide engineering deliverables related to the flare and relief system design to support audit to be done by third party (hired by Owner).
Appears in 2 contracts
Sources: Lump Sum Turnkey Agreement (Cheniere Energy, Inc.), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)
Engineering Design. A. In addition to any other engineering requirements specified in Attachment A or any other provision, Attachment or Schedule of the Agreement, the following services, Drawings and Specifications shall be prepared and provided by Contractor in accordance with Attachment B in respect of all engineering disciplines during engineering of the Project:
1. Completing the engineering design documents, as required, which were developed by Contractor prior to the Agreement Date;
2. Provide engineering support for procurement, transportation, construction, commissioning and assistance to start-up;
3. Performance of all detailed studies, checks and reviews, procedures, and adaptation of design in all disciplines accordingly;
4. Developing and revising drawings sufficient for procurement of materials and Equipment, installation, construction, manufacture, fabrication, commissioning, start-up, testing, operation and maintenance of the Project;
5. Submission of documents for review and comment in accordance with Attachment B;
6. Lead, participate in and action results of technical reviews, including preparation and supply of all required documents for team members;
7. Evaluate and close technical inquiries;
8. Preparation of Equipment data sheets;
9. Preparation of engineering material requisitions and purchase requisitions, and amendments as necessary;
10. Technical evaluation for all major Contractor-Supplied Equipmentequipment;
11. Requisitions, and other technical documents and evaluations for the procurement of all necessary bulk material and Contractor-Supplied Equipment;
12. Development and implementation of a plan for witnessing of factory tests at Vendorsupplier’s shops for major Contractor-Supplied Equipmentequipment;
13. Drawings control, Vendor vendor data and documentation control using a computer database and Contractor’s document control procedure;
14. Provide Vendorsupplier’s recommendations for operating spare parts and prepare final operating spare parts list;
15. Develop list of first fills and start-up consumables (including strainers and filters);
16. Development of technical documents for Subcontracts;
17. Provision of engineering support for procurement, construction and commissioning;
18. Preparation of mechanical catalogues and Vendor vendor data books;
19. Provision of all Record As-Built Drawings and Specifications;
20. Drawings and packages required for tie-ins;
21. Development of Equipment lists, instrument index, line lists;
22. Maintenance documentation for all Contractor-Supplied Equipment equipment provided;
23. Participate in comprehensive safety technical design reviews for E-HAZOP/HAZID/HAZOP/SIL, as required by Owner. An update of electrical HAZOP is not envisioned during detailed engineering. The reviews shall occur and E-HAZOP/HAZID/HAZOP/SIL HAZOP action items shall be closed out before completion of detailed designdesign and IFC. Third party facilitation, paid by Owner, will be used to conduct the review meetings. The following HAZOP/SIL items have been closed. Unless listed below, HAZOP/SIL/Alternate Design Workshop items are unresolved and are excluded: HAZOP Items resolved and incorporated (at EPC execution) [***] SIL Items resolved and incorporated (at EPC execution) [***] For greater clarity, Parties agree that E-HAZOP reviews will be conducted during execution, and, therefore, E-HAZOP items are unresolved and excluded from the scope;
24. Not usedParticipate in Layer of Protection Analysis review to define safety levels of critical control and safety systems not previously completed. Third party facilitation, paid by Owner, will be used to conduct the review meetings;
25. Support fire explosion risk analysis, which will be performed by third party hired by Owner;
26. Support QRA as required, which will be performed by a third party hired by Owner; and;
27. Support independent flare system review audit during detailed design – Contractor will be required to provide engineering deliverables related to the flare and relief system design to support audit to be done by third party (hired by Owner).
Appears in 1 contract
Sources: Fixed Price Separated Turnkey Agreement (Cheniere Energy, Inc.)