Early Work Packages. 6.6.2.1 Early Work Packages may be awarded to the ▇▇▇▇ during the preconstruction phase services of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Work in advance of the agreement between the Owner and CMAR regarding the GMP Proposal for the entire Work. These Early Work Packages will be ready for commencement of their construction before it is appropriate to arrive at an overall GMP for the entire Work. Early Work Package shall be defined as a portion of Work that the Parties agree should be executed during the preconstruction phase services of the Project. 6.6.2.2 Either Owner or the CMAR may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item with reference made to the appropriate GMP Amendment. The ▇▇▇▇’▇ fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears to the Owner’s Budget. The CMAR will be obligated to provide payment and performance bonds in accordance with Article 5 of the General Conditions for the GMP amount of any early Work Package. 6.6.2.3 The Owner may choose to accelerate the completion of certain portions of the design work so that some specific Early Work Packages may be awarded by the CMAR prior to the completion of the remaining Construction Documents or acceptance by the Owner of the GMP Proposal for the entire Work. The CMAR shall verify that the Design Professional has provided the documents necessary to Bid and award any Early Work Package. Any Early Work Package shall contain language which makes those subcontracts 100% assignable to Owner at Owner’s option, in the event this Agreement is terminated, and that the Subcontractors shall be obligated to accept that assignment if it should occur. 6.6.2.4 For any Early Work Package, the CMAR shall submit to Owner a GMP Proposal in accordance with Section 6.6 of this Agreement.
Appears in 1 contract
Early Work Packages. 6.6.2.1 Early Work Packages may be awarded to the ▇▇▇▇ during the preconstruction phase services of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Work in advance of the agreement between the Owner and CMAR ▇▇▇▇ regarding the GMP Proposal for the entire Work. These Early Work Packages will be ready for commencement of their construction before it is appropriate to arrive at an overall GMP for the entire Work. Early Work Package shall be defined as a portion of Work that the Parties agree should be executed during the preconstruction phase services of the Project.
6.6.2.2 Either Owner or the CMAR ▇▇▇▇ may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR ▇▇▇▇ may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item with reference made to the appropriate GMP Amendment. The ▇▇▇▇’▇ fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears to the Owner’s Budget. The CMAR ▇▇▇▇ will be obligated to provide payment and performance bonds in accordance with Article 5 of the General Conditions for the GMP amount of any early Work Package.
6.6.2.3 The Owner may choose to accelerate the completion of certain portions of the design work so that some specific Early Work Packages may be awarded by the CMAR ▇▇▇▇ prior to the completion of the remaining Construction Documents or acceptance by the Owner of the GMP Proposal for the entire Work. The CMAR ▇▇▇▇ shall verify that the Design Professional has provided the documents necessary to Bid and award any Early Work Package. Any Early Work Package shall contain language which makes those subcontracts 100% assignable to Owner at Owner’s option, in the event this Agreement is terminated, and that the Subcontractors shall be obligated to accept that assignment if it should occur.
6.6.2.4 For any Early Work Package, the CMAR ▇▇▇▇ shall submit to Owner a GMP Proposal in accordance with Section 6.6 of this Agreement.
Appears in 1 contract
Early Work Packages. 6.6.2.1 Early Work Packages may be awarded to the ▇▇▇▇ during the preconstruction phase services of the Project to facilitate the early preparation of the Site, purchase long lead time materials and equipment and otherwise accelerate certain portions of the Work in advance of the agreement between the Owner and CMAR ▇▇▇▇ regarding the GMP Proposal for the entire Work. These Early Work Packages will be ready for commencement of their construction before it is appropriate to arrive at an overall GMP for the entire Work. Early Work Package shall be defined as a portion of Work that the Parties agree should be executed during the preconstruction phase services of the Project.
6.6.2.2 Either Owner or the CMAR ▇▇▇▇ may propose Early Work Packages to proceed prior to that time the GMP Proposal for the entire Work is approved by the Owner. Based upon the written agreement of the Parties, the CMAR ▇▇▇▇ may either perform, if selected by the Owner as the successful bidder or proposer, or subcontract such Early Work Packages before the GMP Proposal for the entire Work has been submitted and approved. The approved GMP amount for the scope of Work in any early Work Package shall be included in the subsequent GMP Proposal for the entire Work as an individual line item with reference made to the appropriate GMP Amendment. The ▇▇▇▇’▇ fee for billing purposes for such Early Work Package scope of Work shall not exceed the pro rata portion of the fee that the Cost of Work of the Early Work Package as performed bears to the Owner’s Budget. The CMAR will be obligated to provide payment and performance bonds in accordance with Article 5 of the General Conditions for the GMP amount of any early Work Package.GMP
6.6.2.3 The Owner may choose to accelerate the completion of certain portions of the design work so that some specific Early Work Packages may be awarded by the CMAR ▇▇▇▇ prior to the completion of the remaining Construction Documents or acceptance by the Owner of the GMP Proposal for the entire Work. The CMAR ▇▇▇▇ shall verify that the Design Professional Engineer has provided the documents necessary to Bid and award any Early Work Package. Any Early Work Package shall contain language which makes those subcontracts 100% assignable to Owner at Owner’s option, in the event this Agreement is terminated, and that the Subcontractors shall be obligated to accept that assignment if it should occur.
6.6.2.4 For any Early Work Package, the CMAR shall submit to Owner a GMP Proposal in accordance with Section 6.6 of this Agreement.shall