Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications. (i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable. (ii) In the event that Gatherer would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities. (iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute. (iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities. (v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 2 contracts
Sources: Gas Gathering Agreement (Hess Midstream Partners LP), Gas Gathering Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party Provider or Customer of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party Customer of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering Terminals System Plan and System Budget would be needed to incorporate the installation of such additional facilities. TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**).
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering Terminals System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering Terminals System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 2 contracts
Sources: Terminal and Export Services Agreement (Hess Midstream Partners LP), Terminal and Export Services Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute. TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**).
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 2 contracts
Sources: Crude Oil Gathering Agreement (Hess Midstream Partners LP), Crude Oil Gathering Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**). then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 2 contracts
Sources: Gas Processing and Fractionation Agreement (Hess Midstream Partners LP), Gas Processing and Fractionation Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party Provider or Customer of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party Customer of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law). TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, as applicableAND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**).
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering Terminals System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering Terminals System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering Terminals System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 2 contracts
Sources: Terminal and Export Services Agreement (Hess Midstream Partners LP), Terminal and Export Services Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**). pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 2 contracts
Sources: Gas Processing and Fractionation Agreement (Hess Midstream Partners LP), Gas Processing and Fractionation Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party Provider or Customer of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party Customer of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ ' receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ ' collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable. CERTAIN CONFIDENTIAL PORTIONS OF THIS EXHIBIT WERE OMITTED BY MEANS OF MARKING SUCH PORTIONS WITH BRACKETS (“[***]”) BECAUSE THE IDENTIFIED CONFIDENTIAL PORTIONS (I) ARE NOT MATERIAL AND (II) IS THE TYPE OF INFORMATION THAT THE REGISTRANT TREATS AS PRIVATE OR CONFIDENTIAL.
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering Terminals System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering Terminals System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering Terminals System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 1 contract
Sources: Terminal and Export Services Agreement (Hess Midstream LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ ' receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ ' collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility. CERTAIN CONFIDENTIAL PORTIONS OF THIS EXHIBIT WERE OMITTED BY MEANS OF MARKING SUCH PORTIONS WITH BRACKETS (“[***]”) BECAUSE THE IDENTIFIED CONFIDENTIAL PORTIONS (I) ARE NOT MATERIAL AND (II) IS THE TYPE OF INFORMATION THAT THE REGISTRANT TREATS AS PRIVATE OR CONFIDENTIAL.
Appears in 1 contract
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility. TERMS IN THIS EXHIBIT HAVE BEEN REDACTED BECAUSE CONFIDENTIAL TREATMENT FOR THOSE TERMS HAS BEEN REQUESTED. THE REDACTED MATERIAL HAS BEEN FILED SEPARATELY WITH THE SECURITIES AND EXCHANGE COMMISSION, AND THE TERMS HAVE BEEN MARKED AT THE APPROPRIATE PLACE WITH TWO ASTERISKS (**).
Appears in 1 contract
Sources: Gas Gathering Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ ' receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ ' collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute. CERTAIN CONFIDENTIAL PORTIONS OF THIS EXHIBIT WERE OMITTED BY MEANS OF MARKING SUCH PORTIONS WITH BRACKETS (“[***]”) BECAUSE THE IDENTIFIED CONFIDENTIAL PORTIONS (I) ARE NOT MATERIAL AND (II) IS THE TYPE OF INFORMATION THAT THE REGISTRANT TREATS AS PRIVATE OR CONFIDENTIAL.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 1 contract
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 1 contract
Sources: Gas Processing and Fractionation Agreement (Hess Midstream Partners LP)
Downstream Facilities. Notwithstanding the quality specifications above, if a Downstream Facility notifies either Party of different or additional quality specifications required at any Delivery Point that are more stringent than the specifications shown above, such Party will promptly notify the other Party of any such different or additional specifications as soon as practicable after being notified of such specifications.
(i) Following the Parties’ ' receipt of a notice from a Downstream Facility as described in Section 1.1(b) of the Operating Terms above, the Parties shall promptly meet to discuss such different or additional quality specifications and agree upon the Parties’ ' collective response to such Downstream Facility. Each Party agrees to use its commercially reasonable efforts to meet and agree upon such response within any applicable time limitation imposed by such Downstream Facility, any binding contractual commitment of either Party, or any Governmental Authority (including any applicable Law), as applicable.
(ii) In the event that Gatherer Provider would be required to install any processing or treatment facilities in order to meet any such different or additional Downstream Facility quality specifications, the Parties shall meet to determine (A) what additional facilities would be needed, (B) whether or not the Parties agree that such additional facilities should be installed, and (C) what amendments to the then-current Gathering System Plan and System Budget would be needed to incorporate the installation of such additional facilities.
(iii) In the event that the Parties do not mutually agree (A) that such additional facilities should either be installed or not installed, or (B) on the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then, in each case, the provisions of Section 5.3(e) shall be applied by the Parties with respect to such dispute.
(iv) In the event that the Parties mutually agree (or it is determined pursuant to Section 5.3(e)) (A) that such additional facilities should be installed, and (B) upon the amendments to the then-current Gathering System Plan that would be needed to incorporate the installation of such additional facilities, then Gatherer Provider shall be provided such period of time as would be reasonably needed to install and place into service such additional facilities.
(v) Following the date upon which any such additional facilities are installed and placed into service, such different or additional Downstream Facility quality specifications will be considered as the quality specifications with respect to the applicable Delivery Points under this Agreement for as long as required by such Downstream Facility.
Appears in 1 contract