Delayed completion test. 8.4.1 If a certain engineering lags behind the progress schedule of completion test due to Contractor, it shall take actions to catch up with the progress schedule at its own expenses as agreed in article 4.1.2. 8.4.2 Contractor is held liable for overdue compensation on which as agreed in article 4.5, if the delay of completion test caused by Contractor leads to delay of specified completion date under this Contract. 8.4.3 Completion test organized by Employer. Contractor, without justifiable reasons, failing to complete test according to the progress schedule of completion test decided by leading organization institution, and in 10 days after receiving the notice from leading institution of this test, without justifiable reasons, still has not completed the test, Employer shall therefore have the right to organize the completion test, of which the risks and expenses shall be borne by Contractor. 8.4.4 If Employer’s failure to carry out their duties according to the provisions of the article 8.1.2, results in delayed completion test by Contractor and increased costs, the incurred expenses shall be borne by Employer, and the completion date shall be postponed accordingly when completion test schedule is delayed. Contract Number: SMX-JSZH - [ 2019 ] - [ 035 ]
Appears in 1 contract
Delayed completion test. 8.4.1 If a certain engineering lags behind the progress schedule of completion test due to Contractor, it shall take actions to catch up with the progress schedule at its own expenses as agreed in article 4.1.2.
8.4.2 Contractor is held liable for overdue compensation on which as agreed in article 4.5, if the delay of completion test caused by Contractor leads to delay of specified completion date under this Contract.
8.4.3 Completion test organized by Employer. Contractor, without justifiable reasons, failing to complete test according to the progress schedule of completion test decided by leading organization institution, and in 10 days after receiving the notice from leading institution of this test, without justifiable reasons, still has not completed the test, Employer shall therefore have the right to organize the completion test, of which the risks and expenses shall be borne by Contractor.
8.4.4 If Employer’s failure to carry out their duties according to the provisions of the article 8.1.2, results in delayed completion test by Contractor and increased costs, the incurred expenses shall be borne by Employer, and the completion date shall be postponed accordingly when completion test schedule is delayed. Contract Number: SMX-JSZH - JSZH-[ 2019 ] - ]-[ 035 034 ]