Dayworks. 61.1 If applicable, the Dayworks rates in the Contractor’s bid shall be used for small additional amounts of work only when the Project Manager has given written instructions in advance for additional work to be paid for in that way. 61.2 All work to be paid for as Dayworks shall be recorded by the Contractor on forms approved by the Project Manager. Each completed form shall be verified and signed by the Project Manager within two days of the work being done. 61.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks forms.
Appears in 1 contract
Sources: Contract for Small Works
Dayworks. 61.1 29.1 If applicable, the Dayworks rates in the Contractor’s bid tender shall be used for small additional amounts of work Work only when the Project Manager has given written instructions in advance for additional work to be paid for in that way.
61.2 29.2 All work to be paid for as Dayworks shall be recorded by the Contractor on forms Forms approved by the Project Manager. Each completed form shall be verified and signed by the Project Manager within two days of the work Work being done.
61.3 29.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks forms.
Appears in 1 contract
Sources: Construction Contract