Dayworks. (a) At its sole discretion the Contractor’s Representative may direct that work the subject of a variation be carried out on a dayworks basis. (b) If directed to carry out dayworks, the Subcontractor, as a precondition to any entitlement to payment, each day must record all resources used in carrying out the work the subject of the variation and provide a copy to the Contractor’s Representative. (c) The Subcontractor’s entitlement to payment for dayworks is limited to: (i) the all-inclusive hourly rate agreed with, or determined by the Contractor’s Representative; and (ii) the actual cost of any plant, materials and equipment approved by the Contractor’s Representative to be used or provided, plus 10% of the actual costs.
Appears in 2 contracts
Sources: Subcontract Agreement, Subcontract Agreement