CPM. The Contractor shall prepare in a format and with a level of detail acceptable to the Owner (as described in Exhibit J attached), a detailed CPM schedule incorporating the following: (a) Project activity sequences and durations for on-site construction. (b) Processing of shop drawings. (c) Product data and samples. (d) Delivery of products requiring a long lead time for procurement. (e) The portion of the Project reflecting the Owner’s requirements for priority occupancy.
Appears in 2 contracts
Sources: Contractor Agreement, Contractor Agreement