Common use of Contractor Change Proposal – Process and Implementation Clause in Contracts

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate the Contractor Change Proposal; Where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 (Amendments to Contract); or Serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 37 contracts

Sources: General Contract, Contract, Supply Agreement

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : 1. evaluate the Contractor Change Proposal; Where ; 2. where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : 1. indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 Condition 6 (Amendments to Contract); or Serve or 2. serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 14 contracts

Sources: Provision of Df186 – Mod Data Framework, Contract for Sales Management System, Viking Combined Support Contract

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : (1) evaluate the Contractor Change Proposal; Where ; (2) where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : (1) indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause Condition A2 (Amendments to Contract); or Serve or (2) serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 8 contracts

Sources: Supply Agreement, Supply Agreement, Supply Agreement

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate evaluate the Contractor Change Proposal; Where where necessary, discuss with the Contractor any issues arising and and, following such discussions discussions, the Authority may modify the Authority Notice of Change and the Contractor shall shall, as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause condition A2 (Amendments to Contract); or Serve serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) aboveclause 4.b.(1).

Appears in 6 contracts

Sources: Contract for Pressure Systems Maintenance and Repair, Contract, Contract for the Provision of Safety Training

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate evaluate the Contractor Change Proposal; Where where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause Condition A2 (Amendments to Contract); or Serve serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 6 contracts

Sources: Supply Agreement, Supply Agreement, Supply Agreement

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : (1) evaluate the Contractor Change Proposal; Where ; (2) where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : (1) indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 Condition 6 (Amendments to Contract); or Serve or (2) serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 4 contracts

Sources: Supply Contract, Supply Agreement, Supply and Delivery Agreement

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate evaluate the Contractor Change Proposal; Where where necessary, discuss with the Contractor any issues arising and and, following such discussions discussions, the Authority may modify the Authority Notice of Change and the Contractor shall shall, as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause condition A2 (Amendments to Contract); or Serve or serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) aboveclause 4.b.(1).

Appears in 4 contracts

Sources: Contract for Provision of Services, Supply of Electricity Agreement, Provision of Agency Fuel Cards

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: : (1) Evaluate the Contractor Change Proposal; ; (2) Where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: : (1) Indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 (Amendments to Contract); or or (2) Serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 4 contracts

Sources: Supply Agreement, Supply Agreement, Procurement Contract

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : (1) evaluate the Contractor Change Proposal; Where ; (2) where necessary, discuss with the Contractor any issues arising and and, following such discussions discussions, the Authority may modify the Authority Notice of Change and the Contractor shall shall, as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : (1) indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause condition A2 (Amendments to Contract); or Serve or (2) serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) aboveclause 4.b.(1).

Appears in 4 contracts

Sources: Provision of Differential GPS (Dgps) for Royal Navy Survey Vessels, Team Contract, Contractor Logistic Support Agreement

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate evaluate the Contractor Change Proposal; Where where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 Condition 6 (Amendments to Contract); or Serve serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 2 contracts

Sources: Provision of Ilog Training Framework, Contract

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : 1. evaluate the Contractor Change Proposal; Where ; 2. where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : 1. indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 Condition 6 (Amendments to Contract); or Serve or 2. serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(14b. (1) above.

Appears in 2 contracts

Sources: Manufacture, Supply and Delivery Agreement, Manufacture and Supply Agreement

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate evaluate the Contractor Change Proposal; Where where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause Condition A2 (Amendments to Contract); or Serve or serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) above.

Appears in 2 contracts

Sources: Supply Agreement, Contract for the Supply of Transport Equipment and Auxiliary Products

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: : (1) Evaluate the Contractor Change Proposal; ; (2) Where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: : (1) Indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 (Amendments to Contract); or or (2) Serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(14b(1) above.

Appears in 2 contracts

Sources: Procurement Agreement, Purchase Agreement

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : (1) evaluate the Contractor Change Proposal; Where ; (2) where necessary, discuss with the Contractor any issues arising and and, following such discussions discussions, the Authority may modify the Authority Notice of Change and the Contractor shall shall, as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : (1) indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause clause A2 (Amendments to Contract); or Serve or (2) serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) aboveclause 4.b.(1).

Appears in 1 contract

Sources: Contract for Repair Services

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate evaluate the Contractor Change Proposal; Where where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 Condition 6 (Amendments to Contract); or Serve serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(14b(1) above.

Appears in 1 contract

Sources: Provision of Information Management & Information Technology (Imit) Training Framework

Contractor Change Proposal – Process and Implementation. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate the Contractor Change Proposal; Where necessary, discuss with the Contractor any issues arising and following such discussions the Authority may modify the Authority Notice of Change and the Contractor shall as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause A2 (Amendments to Contract); or Serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(14b(1) above.

Appears in 1 contract

Sources: Contract for Dry Shot Blaster and Tumbler Systems

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : (1) evaluate the Contractor Change Proposal; Where ; (2) where necessary, discuss with the Contractor any issues arising and and, following such discussions discussions, the Authority may modify the Authority Notice of Change and the Contractor shall shall, as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : (1) indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause condition A2 (Amendments to Contract); or Serve or (2) serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) aboveclause 4b(1).

Appears in 1 contract

Sources: Support & Maintenance Agreement

Contractor Change Proposal – Process and Implementation. a. As soon as practicable after the Authority receives a Contractor Change Proposal, the Authority shall: Evaluate : (1) evaluate the Contractor Change Proposal; Where ; (2) where necessary, discuss with the Contractor any issues arising and and, following such discussions discussions, the Authority may modify the Authority Notice of Change and the Contractor shall shall, as soon as practicable, and in any event not more than ten (10) Business Days (or such other period as the Parties may agree) after receipt of such modification, submit an amended Contractor Change Proposal. . b. As soon as practicable after the Authority has evaluated the Contractor Change Proposal (amended as necessary) the Authority shall: Indicate : (1) indicate its acceptance of the Change Proposal by issuing an amendment to the Contract in accordance with Clause condition A2 (Amendments to Contract); or Serve or (2) serve a Notice on the Contractor rejecting the Contractor Change Proposal and withdrawing (where issued) the Authority Notice of Change. . c. If the Authority rejects the Change Proposal Proposal, it shall not be obliged to give its reasons for such rejection. . d. The Authority shall not be liable to the Contractor for any additional work undertaken or expense incurred unless a Contractor Change Proposal has been accepted in accordance with Clause 4b.(1) aboveclause 4.b.(1).

Appears in 1 contract

Sources: Contract for the Provision of Combined Support Services