Computer Scheduling Software. Prepare Project Schedules using current version of a program that has been developed specifically to manage CPM schedules and interface with the Owner’s electronic file of the Bid Milestone Schedule. a) Utilize Primavera P6 or P3 Primavera Project Planner operating system. PRODUCTS 1. Contractor’s Baseline Schedule: Each Contractor shall prepare schedule using a time-scaled PDM network diagram representing the Work of their Contract. Total float time shall be equal to or greater than zero in the Baseline Schedule. a) Coordinate with each Contractor to submit their Baseline Schedule within 15 days of the date established for the Notice to Proceed. Outline significant construction activities for the first 90 days of construction. Include skeleton diagram for the remainder of the Work based on indicated activities. b) Coordinate with each Contractor for the Construction Manager to develop network diagram in sufficient time to submit Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice to Proceed.
Appears in 1 contract
Sources: Construction Management Agreement
Computer Scheduling Software. Prepare Project Schedules using current version of a program that has been developed specifically to manage CPM schedules and interface with the OwnerOWNER’s electronic file of the Bid Milestone Schedule.
a) Utilize Primavera P6 or P3 Primavera Project Planner operating system. PRODUCTS
1. Contractor’s Baseline Schedule: Each Contractor shall prepare schedule using a time-scaled PDM network diagram representing the Work of their Contract. Total float time shall be equal to or greater than zero in the Baseline Schedule.
a) Coordinate with each Contractor to submit their Baseline Schedule within 15 days of the date established for the Notice to Proceed. Outline significant construction activities for the first 90 days of construction. Include skeleton diagram for the remainder of the Work based on indicated activities.
b) Coordinate with each Contractor for the Construction Manager to develop network diagram in sufficient time to submit Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice to Proceed.
Appears in 1 contract
Sources: Construction Management Agreement