COMMUNICATION ARRANGEMENTS. 8.1. Schedule 3 sets out the requirements (if any) which apply for the purposes of Section J5.5.1. 1. Installation, Commissioning, Operation and Maintenance of the Supply Point Measurement Equipment comprised within [ABC]’s Facilities 1.1. [ABC] shall install, commission, operate and maintain the Supply Point Measure m ent Equipment in accordance with OFGEM COP/1c “Code of Practice for all Higher Pressure and all other Low Pressure Meter Installations not covered by COP/1a and COP/1b” and National Grid’s T/SP/ME/1 “Gas Transporter’s Requirements for Gas Measurement Systems Connected to the National Grid Network” and the Institution of Gas Engineers and Managers (IGEM) Recommendations on IGE/GM/4 “Flow Metering Practice for pressures between 38 and 100 Bar”. 2. Maintenance procedures for the Supply Point Measurement Equipment comprised within [ABC]’s Facilities 2.1. [ABC] shall produce a maintenance procedure in accordance with T/SP/ME / 1, IGE/GM/4 and COP/1c for the Supply Point Measurement Equipment before commencement of commissioning for agreement of the Registered User(s) and National Grid. 3. Commissioning procedures for the Supply Point Measurement Equipment comprised within [ABC]’s Facilities 3.1. [ABC] shall produce a commissioning procedure in accordance with T/SP/ME / 1, IGE/GM/4 and COP/1c, and relevant metering standards ISO 5167, ISO 9951, BS 7965, ISO 6976 and AGA8 for the Supply Point Measurement Equipment before commencement of commissioning for agreement of the Registered User(s) and National Grid. [ABC] shall give National Grid and the Registered User(s) reasonable advance notice of the Meter(s) validation at final commissioning and shall at this time provide Meter calibration certificates from an accredited calibration facility for the Primary, Fuel Gas and Auxiliary Meters being commissioned.
Appears in 1 contract
Sources: Network Exit Agreement
COMMUNICATION ARRANGEMENTS. 8.1. Schedule 3 sets out the requirements (if any) which apply for the purposes of Section J5.5.1.. SCHEDULE 1
1. Installation, Commissioning, Operation and Maintenance of the Supply Point Measurement Equipment comprised within [ABC]’s Facilities
1.1. [ABC] shall install, commission, operate and maintain the Supply Point Measure m ent Measurement Equipment in accordance with OFGEM COP/1c “Code of Practice for all Higher Pressure and all other Low Pressure Meter Installations not covered by COP/1a and COP/1b” and National Grid’s T/SP/ME/1 “Gas Transporter’s Requirements for Gas Measurement Systems Connected to the National Grid Network” and the Institution of Gas Engineers and Managers (IGEM) Recommendations on IGE/GM/4 “Flow Metering Practice for pressures between 38 and 100 Bar”.
2. Maintenance procedures for the Supply Point Measurement Equipment comprised within [ABC]’s Facilities
2.1. [ABC] shall produce a maintenance procedure in accordance with T/SP/ME / 1ME/1, IGE/GM/4 and COP/1c for the Supply Point Measurement Equipment before commencement of commissioning for agreement of the Registered User(s) and National Grid.
3. Commissioning procedures for the Supply Point Measurement Equipment comprised within [ABC]’s Facilities
3.1. [ABC] shall produce a commissioning procedure in accordance with T/SP/ME / 1ME/1, IGE/GM/4 and COP/1c, and relevant metering standards ISO 5167, ISO 9951, BS 7965, ISO 6976 and AGA8 for the Supply Point Measurement Equipment before commencement of commissioning for agreement of the Registered User(s) and National Grid. [ABC] shall give National Grid and the Registered User(s) reasonable advance notice of the Meter(s) validation at final commissioning and shall at this time provide Meter calibration certificates from an accredited calibration facility for the Primary, Fuel Gas and Auxiliary Meters being commissioned.
Appears in 1 contract
Sources: Network Exit Agreement
COMMUNICATION ARRANGEMENTS. 8.1. Schedule 3 sets out the requirements (if any) which apply for the purposes of Section J5.5.1.
1. Installation, Commissioning, Operation and Maintenance of the Supply Point Measurement Equipment comprised within [ABC]’s Facilities
1.1. [ABC] shall install, commission, operate and maintain the Supply Point Measure m ent Measurement Equipment in accordance with OFGEM COP/1c “Code of Practice for all Higher Pressure and all other Low Pressure Meter Installations not covered by COP/1a and COP/1b” and National GridGas’s T/SP/ME/1 “Gas Transporter’s Requirements for Gas Measurement Systems Connected to the National Grid Gas Network” and the Institution of Gas Engineers and Managers (IGEM) Recommendations on IGE/GM/4 “Flow Metering Practice for pressures between 38 and 100 Bar”.
2. Maintenance procedures for the Supply Point Measurement Equipment comprised within [ABC]’s Facilities
2.1. [ABC] shall produce a maintenance procedure in accordance with T/SP/ME / 1ME/1, IGE/GM/4 and COP/1c for the Supply Point Measurement Equipment before commencement of commissioning for agreement of the Registered User(s) and National GridGas.
3. Commissioning procedures for the Supply Point Measurement Equipment comprised within [ABC]’s Facilities
3.1. [ABC] shall produce a commissioning procedure in accordance with T/SP/ME / 1ME/1, IGE/GM/4 and COP/1c, and relevant metering standards ISO 5167, ISO 9951, BS 7965, ISO 6976 and AGA8 for the Supply Point Measurement Equipment before commencement of commissioning for agreement of the Registered User(s) and National GridGas. [ABC] shall give National Grid Gas and the Registered User(s) reasonable advance notice of the Meter(s) validation at final commissioning and shall at this time provide Meter calibration certificates from an accredited calibration facility for the Primary, Fuel Gas and Auxiliary Meters being commissioned.
4. Measurement of gas flows at the Supply Meter Point
4.1. The Supply Point Measurement Equipment comprised within [ABC]’s Facilities is or will be the property of and shall be maintained by [ABC].
4.2. All gas offtaken from the National Transmission System, except that referred to in paragraph 4.3(c), shall be measured by the Supply Point Measurement Equipment and all gas measurement data as detailed in the Construction Connection Agreement shall be provided as telemetry signals to National Gas.
4.3. The quantity of gas offtaken at the Supply Meter Point shall be deemed to be the sum of:
(a) the quantities determined by the Primary Meters and the Process Gas Chromatograph in accordance with paragraphs 5 and 8; and
(b) the quantities of Fuel Gas and Auxiliary Gas determined by measurements made by the Fuel Gas Meters and the Auxiliary Gas Meters in accordance with paragraph 6 and the process gas chromatograph in accordance with paragraph 8 or such other methods as may be agreed between the Parties where no such Fuel Gas Meters or Auxiliary Gas Meters exist at the Supply Meter Point.
(c) the unmetered energy quantities determined in accordance with paragraph 9.1 to account for unmetered energy occurring between the Supply Meter Point and Supply Point Measurement Equipment.
Appears in 1 contract