Change Processing. The Construction Manager shall establish and implement procedures for expediting and processing requests for information, Shop Drawings, material and equipment sample submittals, contract schedule adjustments, Change Directives, Change Orders, substitutes, payment requests and the maintenance of logs. The Construction Manager shall maintain daily job reports. The Construction Manager shall be the party to whom requests for information, submittals, Subcontractor schedule adjustments, substitutions, Change Directive requests, Change Order requests and payment requests shall be submitted.
Appears in 3 contracts
Sources: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
Change Processing. The Construction Manager shall will establish and implement procedures for expediting and processing requests for information, Shop Drawings, material and equipment sample submittals, contract schedule adjustments, Change DirectivesMinor Adjustments, Change Orders, substitutes, payment requests requests, and the maintenance of logs. The Construction Manager shall will maintain daily job reports. The Construction Manager shall will be the party to whom requests for information, submittals, Subcontractor schedule adjustments, substitutions, Change Directive Minor Adjustment requests, Change Order requests requests, and payment requests shall will be submitted.
Appears in 1 contract