Change Orders and Change Directives Clause Samples

Change Orders and Change Directives. 4.6.1 The Consultant shall review any Proposal Requests prepared by the A/E prior to their issuance, review Contractor proposals and submit recommendations thereon to the Contracting Authority, Owner, and A/E, assist in negotiating Change Orders and Change Directives in accordance with the Standard Requirements for authorization and execution by the Contracting Authority, Owner, and A/E. 4.6.2 If the Project is administered using the State’s web-based project management software, the Consultant shall receive and recommend Change Orders and Change Directives for approval, using the “Contract Modificationsbusiness process.
Change Orders and Change Directives. Appendix A – Owner’s Requirements;
Change Orders and Change Directives. The Company shall prepare change orders and construction change directives, with supporting documentation and data as deemed necessary by the Company for LVMPD Facilities’ approval and execution in accordance with the Contract Documents, subject to the current unencumbered appropriations of the Project, and may authorize minor changes in the Work not involving an adjustment in the contract sum or an extension of the contract time and which are not inconsistent with the intent of the Contract Documents. Company shall also review change order costs and make recommendations to LVMPD, sign change orders, and issue responses to Request(s) for Information (RFI).
Change Orders and Change Directives. (a) General (i) Developer and TxDOT may (but shall not be obligated to) agree on Change Orders at any time and without limitation as to the subject matter thereof. (ii) The following may be adjusted by Change Orders or Change Directives: provisions for additional or supplemental services from TxDOT that (A) are generally within the scope of the back office services set forth in this Tolling Services Agreement, (B) are consistent with applicable Law and (C) do not adversely affect TxDOT’s ability to maintain its performance in accordance with the Performance Standards, including additional or supplemental services to assist Developer in implementing its ideas, programs and packages for marketing, promotion and enhanced customer service. For the avoidance of doubt, the changes in scope of work set forth in Section 4(l) may be made only by mutually agreed Change Order. (iii) The following may be adjusted by Change Order or Change Directive: terms and provisions of this Tolling Services Agreement (A) as necessary for Developer to implement Change Orders and Directive Letters under the Agreement that relate to or affect the pre-existing terms of this Tolling Services Agreement, including changes in User Classification, provided the adjustment is consistent with applicable Law; and (B) as necessary to comply with applicable Law. (iv) Where the provisions above expressly permit Developer to issue a Change Directive, Developer may issue it whenever the Parties are unable to agree as to the adjustment to any portion of the compensation for TxDOT or to Performance Standards after having attempted in good faith for a period not exceeding ten Business Days to agree on such matters (which period may be extended, however, for an additional ten Business Days if either Party elects to have the proposed Change Directive evaluated by the Independent Engineer pursuant to Section 17(f)). All Change Directives shall provide a written detailed description of the changes, and the proposed basis for adjustments in compensation and Performance Standards (if any). TxDOT shall proceed immediately with the Change Directive, and the Parties shall then negotiate a Change Order expeditiously and in good faith. If the Parties are unable to reach agreement upon the Change Order, TxDOT may assert a claim or cause of action to resolve such dispute under Section 20. (v) Except as expressly provided above or otherwise mutually agreed in writing by the Parties, no provisions of this Tolling Se...
Change Orders and Change Directives. Appendix A – SSG Scope of Work;
Change Orders and Change Directives 

Related to Change Orders and Change Directives

  • Construction Change Directives 1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1 Construction Schedules, Contractor’s 3.10, 3.11, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • CHANGE DIRECTIVE A Change Directive means a written instruction, which shall be deemed incorporated into and forming part of the Agreement, prepared by the Contract Administrator and signed by the Owner directing the Contractor to proceed with a change in the Work prior to or in the absence of the Owner and the Contractor agreeing upon adjustments in the Contract Price and the Contract Time.

  • Change Order The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • CHANGE ORDERS AND AMENDMENTS A. Any alterations, additions, or deletions to the terms of this Agreement, which are required by changes in federal or state law or by regulations, are automatically incorporated without written amendment hereto, and shall become effective on the date designated by such law or by regulation. B. To ensure the legal and effective performance of this Agreement, both parties agree that any amendment that affects the performance under this Agreement must be mutually agreed upon and that all such amendments must be in writing. After a period of no less than 30 days subsequent to written notice, unless sooner implementation is required by law, such amendments shall have the effect of qualifying the terms of this Agreement and shall be binding upon the parties as if written herein. C. Customers have the right to issue a change order to any purchase orders issued to the Contractor for the purposes of clarification or inclusion of additional specifications, qualifications, conditions, etc. The change order must be in writing and agreed upon by Contractor and the Customer agency prior to issuance of any Change Order. A copy of the Change Order must be provided by the Contractor to, and acknowledged by, H-GAC.