Common use of Casualty Repair Work Clause in Contracts

Casualty Repair Work. If, at any time prior to Final Completion, there is any material casualty of any nature (a “Casualty”) to the Land or the Project Improvements or any part thereof, then StadCo shall (a) give the Authority written notice of such Casualty within five (5) days of such Casualty and (b) use all reasonable efforts to promptly secure the area of damage or destruction to safeguard against injury to Persons or property and, promptly thereafter, remediate any hazard and restore the Land and Project Improvements to a safe condition whether by repair or by demolition, removal of debris, and screening from public view. StadCo shall promptly commence and thereafter proceed with reasonable diligence to repair, restore, replace or rebuild the Project Improvements as nearly as practicable to a condition substantially equivalent to that existing immediately prior to such damage or destruction, in accordance with the applicable provisions of this Agreement in which event the Substantial Completion Date and the Project Completion Date shall be automatically extended for such period of time as may be reasonably necessary to perform and complete the Casualty Repair Work. Such repair, restoration, replacement or rebuilding, including temporary repairs for the protection of Persons or other property pending the completion of any such work, remediation of hazards and restoration of the Project Improvements to a safe condition or any demolition and debris removal required are referred to in this Agreement as the “Casualty Repair Work.”

Appears in 2 contracts

Samples: Development Agreement, Development Agreement

AutoNDA by SimpleDocs

Casualty Repair Work. If, at any time prior to Final Completion, there is any material casualty of any nature (a “Casualty”) to the Land or the Project Improvements or any part thereof, then StadCo shall (a) give the Authority written notice of such Casualty within five five‌ (5) days of such Casualty and (b) use all reasonable efforts to promptly secure the area of damage or destruction to safeguard against injury to Persons or property and, promptly thereafter, remediate any hazard and restore the Land and Project Improvements to a safe condition whether by repair or by demolition, removal of debris, and screening from public view. StadCo shall promptly commence and thereafter proceed with reasonable diligence to repair, restore, replace or rebuild the Project Improvements as nearly as practicable to a condition substantially equivalent to that existing immediately prior to such damage or destruction, in accordance with the applicable provisions of this Agreement in which event the Substantial Completion Date and the Project Completion Date shall be automatically extended for such period of time as may be reasonably necessary to perform and complete the Casualty Repair Work. Such repair, restoration, replacement or rebuilding, including temporary repairs for the protection of Persons or other property pending the completion of any such work, remediation of hazards and restoration of the Project Improvements to a safe condition or any demolition and debris removal required are referred to in this Agreement as the “Casualty Repair Work.”

Appears in 1 contract

Samples: Development and Funding Agreement

AutoNDA by SimpleDocs

Casualty Repair Work. If, at any time prior to Final Completion, there is any material casualty of any nature (a “Casualty”) to the Land or the Project Improvements or any part thereof, then StadCo shall (a) give the Authority written notice of such Casualty within five (5) days of such Casualty and (b) use all reasonable efforts to promptly secure the area of damage or destruction to safeguard against injury to Persons or property and, promptly thereafter, remediate any hazard and restore the Land and Project Improvements to a safe condition whether by repair or by demolition, removal of debris, and screening from public view. StadCo shall promptly commence and thereafter proceed with reasonable diligence to repair, restore, replace or rebuild the Project Improvements as nearly as practicable to a condition substantially equivalent to that existing immediately prior to such damage or destruction, in accordance with the applicable provisions of this Agreement in which event the Substantial Completion Date and the Project Completion Date shall be automatically extended for such period of time as may be reasonably necessary to perform and complete the Casualty Repair Work. Such repair, restoration, replacement or rebuilding, including temporary repairs for the protection of Persons or other property pending the completion of any such work, remediation of hazards and restoration of the Project Improvements to a safe condition or any demolition and debris removal required are referred to in this Agreement as the “Casualty Repair Work.”‌

Appears in 1 contract

Samples: Development Agreement