Common use of Capacity Test Clause in Contracts

Capacity Test. The plant will be operated with the following activities to be performed during the Capacity Test: -- Equipment status will be determined in order to establish that all necessary systems and equipment are operational and functional prior to the commencement of the test. Changes in equipment status and the time of status change will be recorded in the operator log. A copy of the operator log will be provided to the test coordinator by operations personnel during the Capacity Test. -- The facility and equipment will be operated within normal design limits of the equipment and in a manner consistent with good utility practices for continuous long-term operation.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction Agreement (Tenaska Georgia Partners Lp), Engineering, Procurement and Construction Agreement (Tenaska Georgia Partners Lp)