Common use of Approval of Changes Clause in Contracts

Approval of Changes. All Change Requests shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (5) business day period shall be deemed approval by the non-requesting party.

Appears in 60 contracts

Samples: Lease (CM Life Sciences III Inc.), Lease (Selecta Biosciences Inc), Lease (EverQuote, Inc.)

AutoNDA by SimpleDocs

Approval of Changes. All Change Requests shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days Business Days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (5) business day Business Day period shall be deemed approval by the non-requesting party.

Appears in 2 contracts

Samples: Lease (NanoString Technologies Inc), Lease (NanoString Technologies Inc)

Approval of Changes. All Change Requests shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (5) business day period shall be deemed approval of such Change Request by the non-requesting party.

Appears in 1 contract

Samples: Lease

Approval of Changes. All Change Requests shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (5) business day period period, if such failure continues for three (3) business days after written notice thereof, shall be deemed approval by the non-requesting party.

Appears in 1 contract

Samples: Sublease (Momenta Pharmaceuticals Inc)

Approval of Changes. All Change Requests shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five three (53) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five three (53) business day period shall be deemed approval by the non-requesting party.

Appears in 1 contract

Samples: Lease (Protagonist Therapeutics, Inc)

Approval of Changes. All Change Requests shall be subject to the other party’s 's prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s 's decision either to approve or object to the Change Request. The non-requesting party’s 's failure to respond within such five (5) business day period shall be deemed approval by the non-requesting party.

Appears in 1 contract

Samples: Lease (Natera, Inc.)

AutoNDA by SimpleDocs

Approval of Changes. All Change Requests that involve a material change to the shell and core shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (5) business day period shall be deemed approval by the non-requesting party.

Appears in 1 contract

Samples: Lease (Silverback Therapeutics, Inc.)

Approval of Changes. All Change Requests shall be subject to the other party’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (5) business day period shall be deemed approval by the non-requesting party. 2.4.

Appears in 1 contract

Samples: Lease (La Jolla Pharmaceutical Co)

Approval of Changes. All Change Requests shall be subject to the other partypatty’s prior written approval, which approval shall not be unreasonably withheld, conditioned or delayed. The Subject to Section 2.4 below, the non-requesting party shall have five (5) business days after receipt of a Change Request to notify the requesting party in writing of the non-requesting party’s decision either to approve or object to the Change Request. The non-requesting party’s failure to respond within such five (( 5) business day period shall be deemed approval by the non-requesting party.

Appears in 1 contract

Samples: Lease (Zosano Pharma Corp)