Additional Outage Protocols Clause Samples

Additional Outage Protocols. 3.1 Seller is to notify Buyer of all planned or Forced Outages. 3.1.1 Outage information provided by Seller is to include at a minimum start and stop time of Outage, capacity out of service (kW), equipment out of service, and reason for Outage. 3.1.2 Planned Outages shall be provided by Seller to Buyer at least four (4) Business Days prior to the start of the requested Outage. Buyer and Seller shall work in good faith to schedule any Planned Outages at mutually convenient dates and times.